slide 1: GAQM CSM-001 Dumps
Certified Scrum Master CSM
For more information:
https://www.dumps4download.com/csm-001-dumps.html
slide 2: Question: 1
You are the Scrum Master and your Development Team of 6 members has completed six
Sprints with thefollowing information:
Sprint 1: 10 pontos
Sprint 2: 11 pontos
Sprint 3: 15 pontos
Sprint 4: 14 pontos
Sprint 5: 15 pontos
Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate
number ofSprintrequired to complete product development
A. 6
B. 5
C. 4
D. 3
Answer: B
Question: 2
Who has the authority to cancel a Sprint
A. The team members
B. The Scrum Master
C. The Product Owner
D. The Project Manager
Answer: C
Question: 3
Why does Scrum prevent Product Owners from changing Product Backlog items that are
being worked on during the Sprint
A. The development team cannot meet their Sprint commitment to complete work if
requirements are changing
B. A Sprint cycle is not enough time for senior management review and approve changes
C. This forces Product Owners to focus on what is really important for the team to develop.
D. The development team must be able to limit the Product Owner authority
slide 3: Answer: C
Question: 4
You are the Scrum Master and the very first Sprint will complete in 5 days. You are creating
a meeting invite forthe Sprint Review to demo the items completed in the Sprint. Who
should you invite as a required attendee tothe Sprint Review
1. Product Owners
2. Development Team
3. Business Users
A. 1 2 and 3
B. 1 and 2 only
C. The entire company
D. 1 only
Answer: B
Question: 5
The Product Backlog ismaintainedby:
A. The Scrum Master
B. The Development Team
C. The Product Owner
D. The Product Owner and Scrum Master
Answer: C
Question: 6
Who determines whether the development team has been assigned enough work in a
Sprint
A. The Development Team
B. The Product Owner
C. The Product Owner and the Scrum Master
D. The Scrum Master
Answer: A
slide 4: Question: 7
The most encouraged time of day to hold a Scrum Daily Meeting is:
A. A beginning of the day
B. Immediately after lunch
C. 4:30 PM
D. 7:00 PM
Answer: A
Question: 8
What artifact shows actual versus planned progress
A. What artifact shows actual versus planned progress
B. Burndown Chart
C. Task Breakdown
Answer: B
CSM-001 Dumps