Docs for C0 Proto Flight Order:
Docs for C0 Proto Flight Order LAT-DS-02049-05 Flex-circuit Cable Schematic Diagram
LAT-DS-00584-08 Flex-circuit C-0 Mechanical Layout
LAT-DS-02377-02 Tracker Tower Flex-circuit Cable C-0 Assembly
LAT-DS-00334-03 Gerber Files for Flex-circuit C-0
LAT-DS-03031-01 TKR Flex cable Stiffener
LAT-TD-xxxx Assembly Process for Proto-flight Tracker Flex Cable Nano Connectors
Numbers to order 11 assembled, 3 bare:
Assembled
(8 + 1 spare) = 9 INFN for Tower Testing
2 DAQ
Bare (delivery when fab’d) :
3 SLAC
To be Done :
To be Done Coordination: Jerry Clinton, Parts: Jeff Tice
Mechanical Layout: Tim O’Heron, Electrical Layout: Dave Nelson
C0:
draw LAT doc number for Stiffener Gerber file, change dimensions in mech. Drawings
Make corrections in assembly drawing
Update “Assembly Process” with resistors, and RPJ comments
C1 – C7 Layout: Same Interface with Grid
Problem Area: C4-C5 Stay Clear on Top
Start PO for Flight Order now
Specs and SOW are signed – off, have ROM
Order Parts from “Flex_cables_2_17”:
Assembly Process Doc :
Assembly Process Doc Responsible: Jerry Clinton, Parts: Jeff Tice
RPJ Message: should the drawing not specify the thermistor to be glued down and then
potted?
In flight cables we will also need to specify potting for the connectors and resistors (or maybe just a conformal coat for the latter).
Should there not be a note on the drawing regarding the cure cycle for the film adhesive (done)?
I would like to make it clear somehow that the film adhesive needs to extend under the metal wings of the connector, not just the main plastic body. This was not done so far at SLAC, but it is important if we are to be sure that the metal shells don't pop off. hartmut:
Update with other parts:
39kW, thermistor, stiffener(?),
Way to TKR Flex Cable : Milestones:
Way to TKR Flex Cable : Milestones 06/23/2003 Start of my clock
08/26/2003 PRR Readiness Review
10/27/2003 TKR Interface Design Report
11/28/2003 Original target for TKR IDD
01/23/2004 New Layout Crew on board
02/10/2004 Finalize interface GRID-TKR Flex cable C0
02/13/2004 Finalize electrical layout cable C0
“You are here”
02/17/2004 Is TKR IDD signed-off?
02/17/2004 PO Start Production of 14 non-flight C0 cables for INFN/DAQ
03/01/2004 ? All cables designed and laid out, ready for PRR
03/12/2004 Tim O’Heron leaves
03/15/2004 ? Start Production of Short Cables
????? PRR,PO! Start Production of Flight Cables
03/15/2004 ? Flight connectors / Parts available ?
04/15/2004 TKR Tower Test cables needed (C0)