Openpit fundamentals

Views:
 
     
 

Presentation Description

No description available.

Comments

Presentation Transcript

Open Pit Mining Fundamentals : 

Open Pit Mining Fundamentals Venkat

Slide 2: 

2 Terminology BENCH: Ledge that forms a single level of operation above which mineral or waste materials are mined from the bench face.

Slide 3: 

2 Terminology BENCH HEIGHT: Vertical distance between the highest point on the bench (crest) and the lowest point or the bench (toe). It is influenced by size of the equipment, mining selectivity, government regulations and safety.

Slide 4: 

2 Terminology BENCH SLOPE or BANK ANGLE : Horizontal angle of the line connecting bench toe to the bench crest.

Slide 5: 

5 BERM: Horizontal shelf or ledge within the ultimate pit wall slope left to enhance the stability of the a slope within the pit and improve the safety. Berm interval, berm width and berm slope angle are determined by the geotechnical investigation. Terminology

Slide 6: 

5 OVERALL PIT SLOPE ANGLE: The angle measured from the bottom bench toe to the top bench crest. It is the angle at which the wall of an open pit stands and it is determined by rock strength, geologic structures and water conditions. Terminology

Slide 7: 

5 The overall pit slope angle is affected by the width and grade of the haul road. Terminology

Slide 8: 

8 HAUL ROADS: During the life of the pit a haul road must be maintained for access. HAUL ROAD - SPIRAL SYSTEM: Haul road is arranged spirally along the perimeter walls of the pit. Terminology

Slide 9: 

9 HAUL ROAD – SWITCH BACK SYSTEM: Zigzag pattern on one side of the pit. HAUL ROAD WIDTH: Function of capacity of the road and the size of the equipment. Haul road width must be considered in the overall pit design. Terminology

Slide 10: 

10 Haul Road Effect on Pit Limits

Slide 11: 

11 ANGLE OF REPOSE: Maximum slope of the broken material. SUBCROP OR ORE DEPTH: Depth of waste removed to reach initial ore. PRE-PRODUCTION STRIPPING: Stripping done to reach initial ore. Terminology

Slide 12: 

12 ULTIMATE PIT LIMITS: Vertical and lateral extend of the economically mineable pit boundary. Determined on the basis of cost of removing overburden or waste material vs. the mineable value of the ore. PIT SCHEDULING: Material may be mined from the pit either in: sequential push backs conventional push backs. Terminology

Slide 13: 

STRIPPING RATIO: Expressed in tons of waste to tons of ore in hard rock open pit operations. Critical and important parameter in pit design and scheduling. AVERAGE STRIP RATIO: Total waste divided by total ore within the ultimate pit. CUTOFF STRIPPING RATIO: Costs of mining a ton of ore and associated waste equals to net revenue from the ton of Ore. Terminology

Slide 14: 

14 Single Working Bench

Slide 15: 

15 Shovel in Working Bench

Slide 16: 

16 Two Working Benches

Slide 17: 

17 Final Pit Limit

Slide 18: 

18 Example Mine 2001 2007 2011

Slide 19: 

21 Pit Sequence (1)

Slide 20: 

22 Pit Sequence (2)

Slide 21: 

23 Pit Sequence (3)

Slide 22: 

24 Pit Sequence (4)

Slide 23: 

25 Section of Pit Sequence

Slide 24: 

25 Thanks