Project Management for Engineering and Construction :Project Management for Engineering and Construction Garold D. Oberlender
Project Management :Project Management The art and science of coordinating people, equipment, materials, money and schedules to complete a specified project on time and with approved cost.
The key to project management :The key to project management Take a task and break it down into smaller, manageable tasks, and compete tasks one-at-a-time
If a given task is too large, break it down into manageable tasks…
What is a project :What is a project A project is a single, non-repetitive enterprise, and because each project is unique, its outcome can never be predicted with absolute confidence.
A project manager must achieve the end results despite all the risks and problems that are encountered.
(PPP) Principal Parties of a Project :(PPP) Principal Parties of a Project Owner
Designer
Construction Contractor
Any may have one person or a team
Each may have different levels of involvement
All required for a successful project
(PPP) Principal Parties of a Project :(PPP) Principal Parties of a Project Owner
Initiates project
Pays for project
sets operational criteria
Identify level of involvement (reports, approvals, job meetings, etc.)
(PPP) Principal Parties of a Project :(PPP) Principal Parties of a Project Designer
Produce design alternates
Design computations
Prepare plans and specifications
Other responsibilities
On-site inspection – daily or periodic
Review shop drawings
Land acquisition
Permits
Budget preparation
(PPP) Principal Parties of a Project :(PPP) Principal Parties of a Project Construction Contractor
Performance of all work in accordance with the contract documents
Labor, equipment, materials and know-how to build
To complete:
Construction estimate
Work plan
Schedule of values
Project schedule
Who does the project manager work for? :Who does the project manager work for? May be owner, designer or contractor…
Each may have a manager
Project manager works for the project.
Project manager’s team may include… :Project manager’s team may include… Owner’s, designer’s and contractor’s manager
Representatives from:
Marketing
Engineering
Finance
Manufacturing
Construction Project Manager
Design Project Manager
Work Managers
Types of management (philosophical) :Types of management (philosophical) Project Management.
Coordination of a one time work by a team of people who (probably) have never previously worked together
Functional Management (discipline management)
Coordination of repeated work of a similar nature, by the same people
[Examples] Design engineering, surveying, estimating, purchasing, crafts & trades
Career – generally starts with functional, progresses to Project management
Sports – head coach, assistant coaches…
Distinguish between Project and Function Management :Distinguish between Project and Function Management Project Management
What must be done
When it must be done
How much will it cost
Coordinating overall needs
Multi-disciplinary focus
Reliance on others
Project Quality
Administrative viewpoint
Generalist’s approach Function Management
How it will be done
Who will do it
Who well it will be done
Coordinating specific needs
Single-discipline focus
Providing technical expertise
Technical quality
Technical viewpoint
A specialist’s approach
Case Study… :Case Study…
Slide 14:Fort Piqua Hotel Restoration Project
Historic Tax CreditsNew Markets Tax CreditsState GrantsLocal FundingPrivate ContributionsHow the City of Piqua funded a $20 million building restoration for $2.4 million city funds :Historic Tax CreditsNew Markets Tax CreditsState GrantsLocal FundingPrivate ContributionsHow the City of Piqua funded a $20 million building restoration for $2.4 million city funds Project Management:
Problem: :Problem: Dilapidated Historic Hotel in center of CBD
Problem: :Problem:
Problem: :Problem: Dilapidated Historic Hotel in center of CBD
New Streetscape, building façade rehab grants and revitalization of the rest of the downtown
Problem: :Problem:
Problem: :Problem: Dilapidated Historic Hotel in center of CBD
New Streetscape, building façade rehab grants and revitalization of the rest of the downtown
Public Library that needs modernization, additional space, and ADA compliance
Three Stories to be told… :Three Stories to be told… History
Financing – Project Management
Uniqueness in design and construction - Project Management
History :History Hotel built in 1891 – Dedication ceremony October 22, 1891
Thriving Hotel for 35 years – rich history…
Theodore Roosevelt & William Howard Taft both spoke from the main balcony during the presidential campaign of 1912
History :History Hotel built in 1891 – Dedication ceremony October 22, 1891
John Phillips Sousa, Harry Houdini, etc.
Centerpiece of local Civil Rights activities
Struggling Hotel for 45 years
Empty Deteriorating Hotel for 35years
Attempts to Restore :Attempts to Restore Three times in 1990s – Private Developers
Hired Architects
Conducted Feasibility Studies
All walked away – no way to privately recoup costs without public participation (grants)
1999 - “Future Piqua II” :1999 - “Future Piqua II” City Wide Strategic Plan
#1 Priority: Resolve the hotel problem
Either restore it or demolish it –passionate public sentiment on both sides
City Commission - Restore if financially possible
Strategy to Restore the Hotel :Strategy to Restore the Hotel Piqua Improvement Corp. (CIC) purchased building (Benefactor gave $200,000)
City = Developer
Anchor Tenant – Flesh Public Library
3 floors, 30,000 SF, expandable to 45,000 sf
Strategy to Restore the Hotel :Strategy to Restore the Hotel Piqua Improvement Corp. (CIC) purchased building (Benefactor gave $200,000)
City = Developer
Anchor Tenant – Flesh Public Library
3 floors, 30,000 SF, expandable to 45,000 sf
Community Banquet facility/Conference Center – old ballroom on top floor
Strategy to Restore the Hotel :Strategy to Restore the Hotel Piqua Improvement Corp. (CIC) purchased building (Benefactor gave $200,000)
City = Developer
Anchor Tenant – Flesh Public Library
3 floors, 30,000 SF, expandable to 45,000 sf
Community Banquet facility/Conference Center – ballroom, top floor
First floor restaurant and coffee shop accessible from library
Where do we start? :Where do we start? Hire Architect – Jeff Wray & Assoc.
Estimate made public in 2004 - $9.5 million
Negotiate with library board
Apply for grants
Project Manager – November, 2004
Historic Tax Credits :Historic Tax Credits Tax Credits help only entities that pay tax
City pays no taxes
Formed LLC – PIC as general partner, Mainstreet Piqua stand-in as limited partner
Sole purpose: realize benefit of the tax credits and build project Now What?
Funding available… :Funding available… City (Hotel Fund)
Library Lease $135,000 for 20 yr
State of Ohio - Grant for Roof
Vertical Brownfield – Clean Ohio Fund Grant
Other State Grants – CDBG etc.
Historic Tax Credits (20%) ***
(That’s good, but not too close…) $2,000,000
$1,400,000
$ 400,000
$1,300,000
$400,000
$2,500,000
$8,000,000
Slide 39:What Would Piqua Look Like With The Hotel?
Slide 40:What Would Piqua Look Like Without The Hotel?
Slide 41:What Would Piqua Look Like With The Hotel?
Slide 42:What Would Piqua Look Like Without The Hotel?
New Markets Tax Credits :New Markets Tax Credits We became aware of NMTC
Like Historic – Need L.P. structure
Unlike Historic - Competitive
What are NMTC? :What are NMTC? 2001 Federal government allocated $3.5 billion, re-allocated each year.
Distributed to CDEs (Community Development Entities) in $50,000,000 allocations
Stipulations for NMTC :Stipulations for NMTC List of eight – you must comply with three
LMI (Low to moderate Income) Census Tract
Environmental – Vertical Brownfield
Local Designation – Blighted condition
We tried to jump in… :We tried to jump in… Need a CDE who is also an investor
Accept bids, December 2005
No CDE
$14,000,000 low bid
No cash
“Complicated?” :“Complicated?” Investors would not commit to project until the city had firm bids in hand
Contractors did not want to provide firm bid prices until all project funding was secure
Gear up for 2006 allocations :Gear up for 2006 allocations Scheduled for May 1
Open Bids May 1
7 Primes - $14,500,000
Soft Costs- $1,500,000
Total Project $16,000,000
This time…
Hurricane Katrina :Hurricane Katrina $3.5 billion
$1 billion for hurricane victims
Compromise - $4.1 billion total
Hold announcements until June 15
Finally – CDE said “yes” :Finally – CDE said “yes” CDE and Investor – hard to find
Had to reduce budget by $1.5 million
No $1.5 million FFE
No $1.5 million Landscaping
Then what?
How to Fill the Gap ($6.5 Million) :How to Fill the Gap ($6.5 Million) New Markets Tax Credits
City Commission add’l borrow
Still $2.5 million to go - $3,000,000
$1,000,000
$4,000,000
Hotel Library Legacy Alliance :Hotel Library Legacy Alliance Local Philanthropists
Asked, “How much?” [$2,500,000]
Asked, “How soon?” [ 10 days ]
In ten days the HLLA returned with $2,600,000 in pledges from nine donors! (Local banker said he would loan total with signed pledge cards only.)
Gap = $0! :Gap = $0! 5 City Commissioners
7 Library Board Members
7 Contracts
20,548 sidewalk inspectors
1 Project with signed contracts and work underway!
Slide 56:Construction Commencement Ceremony December 18, 2006
Slide 57:Contractors on site – January 8, 2007
Slide 58:Exterior Building Restoration – May 1, 2007
The HLLA is back… :The HLLA is back… “Can we raise the funds to complete the banquet facility?”
Lower cost to do it now
Avoid construction disruption after occupancy
Asked, “How much?” [$1,400,000]
Asked, “How soon?” [By September 1, 2007]
Fundraiser underway
Do you think they’ll do it? (Would you like to participate?)
Every once in a while, project managers enter a new arena :Every once in a while, project managers enter a new arena This is what it all came down to…
Bids for 7 contracts returned… :Bids for 7 contracts returned… General Trades $9,341,000
Masonry restoration $276,714
Electrical $$2,237,000
Plumbing $545,000
HVAC $1,858,000
Sprinkler $200,000
Environmental $87,090
Total $14,544,804
Project Managers :Project Managers City of Piqua
Project General Manager
Project Construction Manager
Project Financial Manager
Jeff Wray Architects
Project Manager
Assistant Project Manager
Piqua Public Library
Project General Manager – Library Director
Project Technical Manager – Architect from MKC
Project managers :Project managers Tuttle Construction
Project Manager
Project Superintendent
Debra-Kuempel HVAC – Project Manager
GM Mechanical plumbing – Project Manager
Carey Electric – Project Manager
A-1 Sprinkler – Project Manager
Trisco systems exterior rehab – Project Manager
LVI Environmental – Project Manager
If you are keeping score… :If you are keeping score… 15 Project Managers – 1 project
Started with Partnering Meeting – 8 hours
Outside Consultant
Optional
$10,000 cost paid by contractors
All participated in cost, all attended
Purpose
Establish goals
Procedure for communication
Procedure for changes
Criteria for conflict resolution
who makes the final call
How do we get there?
Weekly job meeting – 14 present every week plus additional
Slide 78:Project Managers at work…
20 concepts of Project Management :20 concepts of Project Management Ensure that one and only one person is responsible for the project scope, budget and schedule
Don’t begin work without a signed contract, regardless of the pressure to start
Confirm that there is an approved scope, budget, and schedule for the project
Lock in the project scope at the beginning and ensure there is no scope growth without approval
Make certain that the scope is understood by all parties, including the owner
Slide 80:Project Managers at work…
20 concepts of Project Management :20 concepts of Project Management Determine who developed the budget and schedule, and when they were prepared
Verify that the budget and schedule are linked to the scope
Organize the project around the work to be performed, rather than trying to keep people busy
Ensure there is an explicit operational work plan to guide the entire project
Establish a work breakdown structure that divides the project into definable and measurable units of work
Slide 82:Project Managers at work…
20 concepts of Project Management :20 concepts of Project Management Establish a project organizational chart that shows authority and responsibilities for all team members
Build the project staff into an effective team that works together as a unit
Emphasize that quality is a must, regardless of cost or how fast it is completed. (If it doesn’t work, it is worthless.)
Budget all tasks, any work worth doing should have compensation. (Clean-up, safety, etc.)
Develop a project schedule that provides logical sequencing of the work required
Slide 84:Project Managers at work…
20 concepts of Project Management :20 concepts of Project Management Establish a control system that will anticipate and report deviations on a timely basis so corrective action can be taken
Get problems out in the open with all persons involved so they can be resolved
Document all work. It may seem irrevelant now, but may be important later
Prepare a formal agreement with appropriate parties whenever there is a change in the project (the proverbial change order.)
Keep the client informed (they pay, and will use the project upon completion.)
Slide 86:Project Managers at work…
Five basic functions of project management :Five basic functions of project management Planning
Organizing
Staffing
Directing
Controlling
Project Manager’s Role in Planning :Project Manager’s Role in Planning Focus planning on the work to be performed
Establish project objectives early so everyone involved knows what is required
Involve all discipline managers and key staff
Establish well-defined milestones
Build contingencies
Avoid reprogramming
Prepare formal agreements for changes
Communicate project plan to define responsibilities
Note: Good plans are only good if implemented
Project Manager’s Role in Organizing :Project Manager’s Role in Organizing Organize the project around the work to be accomplished
Develop a work breakdown that divides project into measurable units of work
Establish a project organization chart showing who does what
Define clearly the authority and responsibility for all project team members
Project Manager’s Role in Staffing :Project Manager’s Role in Staffing Define clearly the work to be done; work with department heads to select team members
Provide in effective orientation (project goals and objectives) at beginning of the project
Explain what is expected of each team member, and how role fits into total project
Solicit each team member’s input to clearly define and agree upon scope, budget and schedule
Project Manager’s Role in Directing :Project Manager’s Role in Directing Serve as effective leader in coordinating all important aspects of the project
Show interest and enthusiasm, with “can-do” attitude
Be available to project staff, get problems out in the open, and work out problems cooperatively
Analyze problems early for early solutions
Obtain resources needed to accomplish tasks
Recognize each person’s importance, compliment good work, guide in correcting mistakes, build effective team
Project Manager’s Role in Controlling :Project Manager’s Role in Controlling Maintain record of planed and actual work accomplished to measure performance
Maintain milestone chart
Maintain monthly project cost chart
Keep records of meeting, conversations and agreements
Keep everyone informed – no surprises
Project Team :Project Team Effective teamwork is essential in a successful project. Must start early, maintain throughout the project.
(Remember that partnering meeting?)
How do you build a team? :How do you build a team? Communication
Common goal – not competitors
Everyone knowledgeable
Continuity – avoid turnover
Keep peripheral players engaged
Technical and non-technical words like:
Respect, kindness, responsibility, honesty, dignity
Motivating Teams :Motivating Teams Maslow’s hierarchy of Needs Basic Comfort Needs – food, clothing, shelter Safety Needs – job security Belonging Needs –peer acceptance Ego or Self-Esteem Needs (recognition) Self fulfillment needs (power, wealth, influence
Conflict Management :Conflict Management It is inevitable that conflicts among team members will arise. The manager must realize that conflicts can actually be beneficial if resolved I an appropriate manner.
Conflict Management :Conflict Management Withdrawal
Smoothing (a path)
Often temporary
Fogging
Compromise (bargaining)
Reoccurrence
Confrontation
Manager must realize how much authority he or she has
Consensus :Consensus Solution by which all parties can abide
Voting, trading, averaging
Avoid insults, threats, offensive comments or defensive actions
Mutual Respect
Project Management :Project Management The art and science of coordinating people, equipment, materials, money and schedules to complete a specified project on time and with approved cost.