slide 1:

Project Management Professional PMP Based on PMBOK 6th Edition 2018 Exam Preparation Training Course www.ReadytoTrainMaterials.com

slide 3:

Our collection of business training courses – enhanced with beautiful graphics photos videos and animation – instantly gives you the quickest and easiest way to make your training sessions look incredible. You can be confident we’ll have exactly what you need when you need it 24/7 for every training need topic occasion and goal. Ready to Train for Training Materials

slide 4:

Established in 1969 and headquartered outside Philadelphia Pennsylvania USA the Project Management Institute PMI is the world’s leading for project management professional association with 500082 Project Management Professionals PMP. Project Management Institute

slide 5:

PMI membership fee 129/Year PMP exam fee for members 405 PMP exam fee for non-members 555

slide 6:

A widely recognized credential – currently the most sought after certification in the world. Certification has created a world-wide consistency for project terms processes and standards. Benefits of PMP Certification

slide 7:

Is it worth to be PMP Certified  Salary: The PMP certification has a positive effect on the Project Manager’s salary.  Market Demand: The demand for the PMP is big and it’s growing every day and there is no sign that this demand will lessen in time. In fact the demand has actually increased even with the 2008-2009 recession.  Prestige and Recognition: it is a prestigious certification with difficult eligibility criteria a hard test as well as requiring constant maintenance e.g. acquiring PDUs. The PMP certification is highly regarded both in the United States and internationally.  Increased Project Management Knowledge: Studying for the PMP will help the applicant learn new Project Management concepts or understand concepts better. 7

slide 8:

8 of Questions of Domain Domains 23 13 Initiating 42 24 Planning 53 31 Executing 43 25 Monitoring and controlling 14 7 Closing 175 Total number of scored questions 25 Total number of unscored questions 200 Total number of questions The Exam Consists Of 5 Basic Domains

slide 9:

Educational Background PM Experience PM Education High School Diploma Associate’s Degree or Global Equivalent • 60+ Months • 7500+ Hours 35 Contact Hours Educational Background PM Experience PM Education Bachelor’s Degree or Global Equivalent •36+ Months • 4500+ Hours 35 Contact Hours PMP Certification Eligibility Requirements

slide 10:

Months must not overlap Hours may overlap The experience in project during last 8 years PMP Certification Eligibility Requirements

slide 11:

Is recognized standard of project management knowledge. Provides guidelines rules and characteristics for project management. Project Management Body of Knowledge PMBOK This standard is widely accepted and when consistently applied help you your global peers and your organization to achieve professional excellence.

slide 12:

Chapter One Introduction

slide 13:

What is a Project

slide 14:

Temporary Endeavor With a beginning and an end date Not an on-going effort A unique product service or result What is a Project

slide 15:

What is a Project A unique service or a capability to perform a service e.g. a business function that supports or distribution A unique product that can be either a component of another item an enhancement or correction to an item or a new end item in itself e.g. the correction of a defect in an end item

slide 16:

Projects Drive Change Projects drive change in organizations. From a business perspective a project is aimed at moving an organization from one state to another state in order to achieve a specific objective

slide 17:

• Goodwill • Brand recognition • Public benefit • Trademarks • Strategic alignment • Reputation Projects Enable Business Value Creation value is the net quantifiable benefit derived from a business endeavor. The benefit may be tangible intangible or both. • Monetary assets • Stockholder equity • Utility • Fixtures • Tools • Market share Examples of tangible elements include Examples of intangible elements include

slide 18:

Project Initiation Context P r o j e c t Satisfy stakeholder requests or needs Create Improve or fix products processes or services Meet Regulatory local or social requirements Implement or change business or technological strategies

slide 19:

Importance of Project Management

slide 20:

The Importance of Project Management Meet business objectives Satisfy stakeholder expectations Be more predictable Increase chances of success Deliver the right products at the right time Resolve problems and issues Respond to risks in a timely manner

slide 21:

Example: The Website Creation Project Consider a project authorized by a firm to create an intranet website that would display its employee related information. The outcome of the project is the website and the duration will depend on the complexity and size of the work involved. The project will come to an end when the website is posted on the server and is ready for use by appropriate users.

slide 22:

One of the major petrochemical companies has set up a new refinery to meet its increasing market demand. The company plans to break-even in three years by achieving the desired volume of output from its new plant. Once the new plant is set up the operations to be carried out in the new branch include daily production routine maintenance of the plant wages and salary credits to employees purchase of raw materials grievance handling logistics and supply of finished products to the market. Example: Operations in a Petrochemical Industry

slide 23:

Relationship of Project Program Portfolio and Operations Management Program and project management focus doing programs and projects the “right” way and Portfolio management focuses doing the “right” programs.

slide 24:

24 PAGE // • A program is defined as a group of related projects subprograms and program activities managed in a coordinated way to obtain benefits not available from managing them individually. • Project may or may not be part of a program but a program will always have projects • Project within a program are related through the common outcome or collective capability. • A portfolio refers to projects programs sub portfolios and operations managed as a group to achieve strategic objectives The projects or programs of the portfolio may not necessarily be interdependent or directly related. Programs and Portfolio

slide 25:

25 PAGE // Portfolios Programs and Projects Portfolio management aligns portfolios with organizational strategies by selecting the right programs or projects prioritizing the work and providing the needed resources. Program management harmonizes its program components and controls interdependencies in order to realize specified benefits. Project management enables the achievement of organizational goals and objectives

slide 26:

Project Life Cycle

slide 27:

Project Life Cycle Project Phase 1 Project Phase 2 Project Phase 3 Project Phase 4 Initiation Conclusion Handoff Handoff Handoff Gates Gates Gates Deliverables Deliverables Deliverables

slide 28:

Project Life Cycle Feasibility Planning Design Production Turnover Startup Construction

slide 29:

Project Life Cycle Project phases differ from project to another Requirement Design Program Test Implement IT Project

slide 30:

A project phase is a collection of logically related project activities that culminates in the completion of one or more deliverables. The phases in a life cycle can be described by a variety of attributes. Project Life Cycle

slide 32:

32 Questions Samples

slide 33:

Exercise Q1. The estimate for a task is O 3 days P 7 days M 4 days. What is the standard deviation of the task • A. 5/6 of a day. • B. 2/3 of a day. • C. 1 ½ days. • D. 5 2/3 days.

slide 34:

Exercise Q1. The estimate for a task is O 3 days P 7 days M 4 days. What is the standard deviation of the task • A. 5/6 of a day. • B. 2/3 of a day. • C. 1 ½ days. • D. 5 2/3 days. Solution: SD P-O/6 7-3/6 2/3

slide 35:

Exercise Q2. You are the project manager for a new project and have figured out the following dependencies: • Task 1 can start immediately and has an estimated duration of 3 weeks • Task 2 can start after Task1 is completed and has an estimated duration of 3 weeks • Task 3 can start after Task 1 is completed and has an estimated duration of 6 weeks • Task 4 can start after Task 2 is completed and has an estimated duration of 8 weeks • Task 5 can start after task 4 is completed and after Task 3 is completed . This task takes 4 weeks. • What is the duration of the critical path • A. 18.5 weeks -B. 19 weeks -C. 20 weeks -D. 18 weeks

slide 36:

Exercise Q3. A project has three critical paths. Which of the following BEST describes how this affects the project • A. It makes it easier to manage. • B. It increases the project risk. • C. It requires more people. • D. It makes it more expensive.

slide 37:

Exercise Q4. You are taking over a project and determine the following: Task B has an early finish of day 3 a late finish of day 6 and an early start of day 2. Task L is being done by a hard-to-get resource. The CPI is 1.1 and the SPI is 0.8. Based on the information above what would you be most concerned about • A. Float. • B. Resources. • C. Cost. • D. Schedule.

slide 38:

Exercise • You are the project manager for a project with the following network diagram. Studying the diagram which path is the critical path A. ABCD B. EBCD C. EFH D. EGH

slide 39:

Exercise • You are the project manager for a project with the following network diagram. Studying the diagram which path is the critical path ✓ B is the critical path because EBCD is the longest path to completion at 18 days.®˚ A C and D are incorrect because these paths have float. For more information

slide 40: