Financial Update

Views:
 
Category: Education
     
 

Presentation Description

A December 2008 financial review of flood-related construction and a budget outlook based on anticipated reductions in state aid.

Comments

Presentation Transcript

Financial Update 2007-08 General Fund & Flood Restoration Project : 

Financial Update 2007-08 General Fund & Flood Restoration Project December 18, 2008

Slide 2: 

FINANCIAL & BUDGET UPDATE 2008-09 Revenue Budgets at Risk Sales tax & interest income projected shortfall - $180,000 2008-09 Expenditure Budgets Favorable Froze $200,000 in General Fund Equipment & Supplies Savings available to offset revenue shortfalls, tax certiorari claims, or provide 2009-10 Budget flexibility 2009-10 State Aid Cut $178,066 (10.42%) in Governor’s proposed budget

Slide 3: 

Initial Insurance Recoveries $1,500,000 July 10, 2007 Referendum $12,200,000 May 20, 2008 Referendum $1,779,199 May 20, 2008 Referendum $6,607,862 $22,087,061 PROJECT FINANCIAL OVERVIEW BUDGET

Slide 4: 

PROJECT FINANCIAL OVERVIEW Clean-up & Restoration $2,886,789 Asbestos Abatement $343,000 C & D Wing $5,328,200 A & B Wing $4,018,950 A, B, C, D Total Contingency $1,583,551 Soft Costs $1,318,709 Boiler / Switchgear Reloc. $6,607,862 $22,087,061 BUDGETS as of Sept. 1, 2008

Slide 5: 

PROJECT FINANCIAL OVERVIEW FEMA $9,473,330 NYSEMO $3,157,776 Insurance Recoveries $6,811,803 Bronxville Taxpayers (12%) $2,644,152 $22,087,061 PROJECTED REIMBURSEMENTS

Slide 6: 

A, B, C, D CONTINGENCY USAGE