DTP Seremban - Gemas

Views:
 
Category: Entertainment
     
 

Presentation Description

No description available.

Comments

Presentation Transcript

Slide 1: 

1 Contractor : IRCON International Ltd Contract Cost : RM 3,450,000,000 Progress Payment : RM 804,937,190 Site Possession : 18 Jan 2008 Completion Date: 17 Jan 2012 PMC : KLIA Consultancy Services Sdn Bhd Progress : Planned (28.37%) Actual (28.95%) Involves construction of 98km double track, 6 stations and installation of modern signalling, communication and electrification system. ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS Preliminary works such as soil improvement, earthwork, site clearing, piling and structural works at Btg Melaka, Sg. Gadut viaduct, bridges and culverts are in progress

Slide 2: 

2 Installation Formwork (Wall) at Box Culvert No. 63 Earthwork filling at CH 520.800 - CH 521.300 Fixing rebar for culvert C9 at CH 468.668 Construction of stone column at CH 546.600 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS

Slide 3: 

3 ISSUES LAND ACQUISITION ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS

Slide 4: 

4 Extension of Time – EOT IRCON has submitted the application for Extension of Time – EOT via a letter dated 25 May 2009. In the application, IRCON has listed 4 main causes of delay: Land acquisition, Squatters eviction, Finalization of Sg. Gadut Station location and Deletion of tunnel to be replaced by tunnel by-pass. Therefore, completion date for 1st Milestone (Seremban-Sg. Gadut) is requested from 17 July 2010 to 25 December 2010 and overall project completion up to Gemas from 17 January 2012 to 21 September 2012. Status KLIA Consult has evaluated and make a recommendation to the KTMB on 15 July 2009 for review. Recommendation by KLIA Consult: Extended completion 1st Milestone (Seremban - Sg. Gadut) to 25 December 2010. Extended completion overall project to 16 August 2012. ISSUES ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS

Slide 5: 

5 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES

Slide 6: 

6 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES

Slide 7: 

7 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES

Slide 8: 

8 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS ISSUES Finalization of VO for tunnel