Slide 2:
2 Installation Formwork (Wall) at Box Culvert No. 63 Earthwork filling at CH 520.800 - CH 521.300 Fixing rebar for culvert C9 at CH 468.668 Construction of stone column at CH 546.600 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS
Slide 3:
3 ISSUES
LAND ACQUISITION ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS
Slide 4:
4 Extension of Time – EOT
IRCON has submitted the application for Extension of Time – EOT via a letter dated 25 May 2009. In the application, IRCON has listed 4 main causes of delay:
Land acquisition,
Squatters eviction,
Finalization of Sg. Gadut Station location and
Deletion of tunnel to be replaced by tunnel by-pass.
Therefore, completion date for 1st Milestone (Seremban-Sg. Gadut) is requested from 17 July 2010 to 25 December 2010 and overall project completion up to Gemas from 17 January 2012 to 21 September 2012.
Status
KLIA Consult has evaluated and make a recommendation to the KTMB on 15 July 2009 for review.
Recommendation by KLIA Consult:
Extended completion 1st Milestone (Seremban - Sg. Gadut) to 25 December 2010.
Extended completion overall project to 16 August 2012. ISSUES ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS
Slide 5:
5 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES
Slide 6:
6 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES
Slide 7:
7 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS CRITICAL ISSUES
Slide 8:
8 ELECTRIFIED DOUBLE TRACK PROJECT SEREMBAN - GEMAS ISSUES Finalization of VO for tunnel