slide 1: Free PMP® Exam
Sample Question
pm-exam-simulator.com
slide 2: PMP® Exam Sample Question
Presented by Cornelius Fichtner PMP
PMI PMP CAPM PgMP PMI-ACP PMI-SP PMI-RMP and PMBOK are trademarks of the Project Management Institute Inc. PMI
has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes
no warranty guarantee or representation expressed or implied as to the accuracy or content. Every attempt has been made by
OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for
the PMP certification exam. However OSP International LLC accepts no legal responsibility for the content herein. This document
should be used only as a reference and not as a replacement for officially published material. Using the information from this
document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied
or expressed by OSP International LLC.
slide 3: Provided by
www.pm-exam-simulator.com
This presentation showcases free sample
questions to help you study for the PMP exam
slide 4: Which of the following buffers are placed at the
end of the critical chain to protect the target
finish date from slippage
slide 5: Feeding Buffer
Project Buffer
Free Buffer
Activity Buffer
slide 6: This buffer protects the target finish
date from moving and is intended to
protect the project end date.
slide 7: Project Buffer
slide 8: A project buffer is placed at the end of the critical chain
to protect the target finish from slippage along the
critical chain. On the other hand feeding buffers are
placed at those points in the chain where tasks that are
not on the critical path feed into the critical path.
Free buffers and activity buffers are not
used in critical chain.
slide 9: Which of the following statements regarding
WBS templates is incorrect
slide 10: They are always present in
Organizational Process Assets
They provide a starting point for WBS
creation
They may help determine the
appropriate level of detail required
They enhance cross-project WBS
consistency
slide 11: WBS templates can help you create
your project WBS.
slide 12: They are always present in Organizational
Process Assets
slide 13: WBS templates can be found in
Organizational Process Assets but we
cannot say they will always be
available.
slide 14: According to the PMBOK Guide which of the
following is not a valid activity dependency
slide 15: Mandatory Dependency
Core Dependency
External Dependency
Discretional Dependency
slide 16: This question references the
Sequence Activities process.
slide 17: This question references the Sequence
Activities process.
slide 18: The PMBOK Guide recognizes four types of dependencies
Mandatory Discretionary Internal and External. The PMBOK Guide
doesnt recognize "Core Dependencies“ as a type of dependency.
Did it confuse you that one of the answers used the term
"Discretional Dependencies“ instead of "Discretionary
Dependencies" Expect that even on the actual PMP exam you will
come across questions where terminology does not exactly match
the PMBOK Guide. Even considering that "Discretional
Dependencies" is not the exact same term as "Discretionary
Dependencies" "Core Dependencies" is even less correct and
therefore the correct answer."
slide 19: Get more free sample questions from