Free PMP Exam Sample Questions

Views:
 
Category: Education
     
 

Presentation Description

Free sample questions that will help and guide you in studying for the PMP exam.

Comments

Presentation Transcript

slide 1:

Free PMP® Exam Sample Question pm-exam-simulator.com

slide 2:

PMP® Exam Sample Question Presented by Cornelius Fichtner PMP PMI PMP CAPM PgMP PMI-ACP PMI-SP PMI-RMP and PMBOK are trademarks of the Project Management Institute Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty guarantee or representation expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

slide 3:

Provided by www.pm-exam-simulator.com This presentation showcases free sample questions to help you study for the PMP exam

slide 4:

Which of the following buffers are placed at the end of the critical chain to protect the target finish date from slippage

slide 5:

Feeding Buffer Project Buffer Free Buffer Activity Buffer

slide 6:

This buffer protects the target finish date from moving and is intended to protect the project end date.

slide 7:

Project Buffer

slide 8:

A project buffer is placed at the end of the critical chain to protect the target finish from slippage along the critical chain. On the other hand feeding buffers are placed at those points in the chain where tasks that are not on the critical path feed into the critical path. Free buffers and activity buffers are not used in critical chain.

slide 9:

Which of the following statements regarding WBS templates is incorrect

slide 10:

They are always present in Organizational Process Assets They provide a starting point for WBS creation They may help determine the appropriate level of detail required They enhance cross-project WBS consistency

slide 11:

WBS templates can help you create your project WBS.

slide 12:

They are always present in Organizational Process Assets

slide 13:

WBS templates can be found in Organizational Process Assets but we cannot say they will always be available.

slide 14:

According to the PMBOK Guide which of the following is not a valid activity dependency

slide 15:

Mandatory Dependency Core Dependency External Dependency Discretional Dependency

slide 16:

This question references the Sequence Activities process.

slide 17:

This question references the Sequence Activities process.

slide 18:

The PMBOK Guide recognizes four types of dependencies Mandatory Discretionary Internal and External. The PMBOK Guide doesnt recognize "Core Dependencies“ as a type of dependency. Did it confuse you that one of the answers used the term "Discretional Dependencies“ instead of "Discretionary Dependencies" Expect that even on the actual PMP exam you will come across questions where terminology does not exactly match the PMBOK Guide. Even considering that "Discretional Dependencies" is not the exact same term as "Discretionary Dependencies" "Core Dependencies" is even less correct and therefore the correct answer."

slide 19:

Get more free sample questions from free.pm-exam-simulator.com

authorStream Live Help