Presentation Transcript
Katy Freeway : Katy Freeway 40 mile section of IH 10 from downtown Houston to the Brazos River
Constructed in the 1960’s
Design capacity of 79,200 vehicles per day
Pavement design life of 20 years
Part of Interstate Highway System
Maintenance cost $ 49,375 per mile
Katy Freeway - RealityGRIDLOCK : Katy Freeway - Reality GRIDLOCK 207,800 vehicles per day
11 hours daily congestion
30 to 40 year old pavement
Annual maintenance costs of $ 197,500/mile (4 times normal highway maintenance costs)
Slide5 : 23 mile section from IH 610 to Fort Bend County line
8 main lanes, 2 managed lanes, 6 feeder lanes
Construction 2003 - 2009
10 Sections
Beginning at east and west ends working to center
First construction contract awarded June 11, 2003
Slide6 : $ 2,400,000,000
CONSTRUCTION COST
(excludes ROW,utilities)
UTILITY ADJUSTMENTS : UTILITY ADJUSTMENTS Expense of TxDOT’s ROW Division
ROW acquisition,relocation assistance,utility relocation $599,000,000
Construction period spans 2003-2009
Annual Statewide Budget - $300,000,000 for all TxDOT ROW Division
Katy utility adjustments alone will be one-third of ROW Division’s budget for three years running
CenterPoint Energy Work : CenterPoint Energy Work 40 miles of OH distribution
42 underground distribution crossings
21.5 miles of Entex gas lines
Fiber optic reroute and one T-comm antennae
5.7 miles OH Transmission 138kV double circuit converted to UG
3 Substations modified for UG Transmission
$ 110,000,000 : $ 110,000,000 Transmission
Substation
Overhead Distribution
Underground Distribution
Fiber Optics
Entex
28 Contracts over 2003 - 2006
Bureaucratic Red Tape : Bureaucratic Red Tape Unprecedented amount of Bureaucratic red tape
Extended review/approval time for Utility Adjustment contracts
Hesitant to make decisions
Disconnect between TxDOT’s local office and Austin
TXDOT : TXDOT Contract required for relocations prior to start of any construction
Austin-TXDOT review/approval of contracts
Construction overhead cost issue
431 parcels required for project .Not all parcels acquired prior to construction letting
GEC (PB) controls project
Project Website established
CenterPoint Energy Underground Distribution : CenterPoint Energy Underground Distribution 45 locations with proposed underground
42 crossings of I-10 (Katy Freeway)
90 estimates/work orders
Plan & profile drawings and traffic control plans - 120 drawings, 80 traffic control [plans
CEHE : CEHE Drawing review required by all utilities through GEC - PB
Project crossed ROW of several governmental agencies
TXDOT
Harris County Flood Control
Army Corp of Engineers
City of Houston
Hedwig Village
Spring Valley
Hunters Creek
CEHE : CEHE TXDOT lacked numerous parcels but still expedited construction schedule
Directional bores
3 dry bore crossings
Existing easements, required temporary construction easements for work area
City permits - lane closures,street cuts
CEHE Distribution Underground Status : CEHE Distribution Underground Status 10 Sections (42 crossings total)
24 crossings complete
Sections 1,2,8,9,10 - 100% complete
8 crossings under construction
7 on hold - require ROW by TXDOT
3 crossing scheduled for 2006
Catch the
buzz on authorSTREAM
Copyright © 2002-2008 authorSTREAM. All rights reserved.