Slide 2:
Chamber dressing – Critical items (2) LV boards Prototype is ok - In one month we should have all the boards Then burn-in should be done (waiting for firm offer) CERN board still not defined HV connector Mould ready to prepare (this week) a batch of connectors Then we must qualify it through CERN TIS Once OK, the construction is fast (1-2 weeks) HV filter A prototype with CAEN HV module has been tested. The connection to the chamber to be defined CARDIAC Accordingly to Adriano, (mid-end) November we should receive a large sample of boards
Slide 3:
Chamber dressing – Critical items (3) Chamber dressing – as expected – is not an easy job Not all the pieces are there at the same time (at least at the beginning) Certainly one could start with the mechanical work A trained staff of 2 people can prepare 3 chambers per day (this has been verified) We have to test how long we need to setup the FEE and to test it 3 working areas (3-4 people) could meet the requirement of 2 ch/day INFN has to setup (12*2+24*4+96=216) chambers by the start of their commissioning at CERN If Tzero = Nov. 1st, then 110 working days are needed (+Xmas holidays): 22 weeks bring us to mid Apr. (barely enough for chamber installation)