Presentation Transcript
Energy-Efficient Kiln for BrickmakingSeptember 17, 2003 : Energy-Efficient Kiln for Brickmaking September 17, 2003 Donald J. Aumann, PE PIER Buildings Program
Introduction : Introduction Presenting on behalf of Clint Lowell from Energy Commission Efficiency Division
Don did the report in 1999 while working as a consultant …coincidence that I joined CEC
CEC project connection from administering US Department of Energy funds
No new information since 1999 report
Outline : Outline Background
Old kiln technology
New kiln technology
Startup issues
Results—business and technical
Background : Background Pacific Clay Plant
Located about 100 km east of Los Angeles
Existing since late 1800s
Extensive production of bricks, pavers, & pots
Background : Background Used 1950s vintage kilns
Increased product demand in early 1990s …need to increase production capacity
Old Kiln Technology : Old Kiln Technology Large mass of bricks on each kiln car (2 meters high)
High-refractory kiln cars
Relatively low heat transfer rate
Search for New Kiln : Search for New Kiln International search
Pick US technology from Swindell Dressler (www.swindelldressler.com)
Pacific Clay was 2nd installation (1st was in Australia)
Initial Project Cost : Initial Project Cost
Project Schedule : Project Schedule Activity Planned Actual .
Begin design July 1995 July 1995
Construction complete Sept. 1996 April 1996
Extend TK-4 none Dec. 1996
Proper TK-4 operation Jan. 1997 Dec 1996
Construction/Start-Up Issues : Construction/Start-Up Issues County zoning/regulations change …Raise plant 0.6 meters …Improve fire protection …Increased cost $0.5 million to $7.8 million
35% initial production loss rate …Expected 1–2% loss rate …Cool-down zone too short …Extend kiln 7 meters immediately achieve 1–2% loss rate
Start-Up Labor Issues : Start-Up Labor Issues New production line is more sophisticated/automated …4-hour backlog requires continuous operation (old kilns had 2.6 day backlog) …Continuous full-staffing required …Continuous supervision required
Labor summary …Old plant required two low-skilled crews …New plant requires four high-skilled crews
Technical Performance : Technical Performance Characteristic Old New Improvement
Production capacity (tons/year) 30,000 60,000 100%
Burner rating (106 Btu/hr) 29 25.9 Na
Production loss (%) 10 5 50%
Firing plus drying time (hours) 96 48 50%
Exact duration depends on product requirements, with approximately 50% of the time for drying.
Preheat time (cold start, hours) 96 24 75%
Energy/Emissions : Energy/Emissions Characteristic Old New Improvement
Natural gas use (therms/ton) 67.3 43.6 35%
Electricity use (kWh/lb brick) 0.0426 0.0448 -5%
NOx emissions (lb/106 Btu gas) 0.056 0.062 -11% lb./ton brick 0.377 0.270 28%
(NOx for “oxidizing” firing)
Operating Cost Comparison : Operating Cost Comparison Cost Component Pre-TK-4 Post TK-4 Savings $/ton $/ton
Gas Cost 17.51 11.34 35.2%
Electricity Cost 7.76 8.17 -5.3%
Labor Cost 12.81 14.03 -9.5%
Maintenance Cost 13.02 9.61 26.2%
Total 51.10 43.15 15.6%
Suggestions for Future Plants : Suggestions for Future Plants Adopt Different Production Layout
Use more kiln cars
Include increased kiln car storage
Provide 2-day backlog Lower labor costs from using only two crews
Summary : Summary Vice President Allen Cunningham
“Installing this new kiln is like having children…when you’re done, you’re glad you did it.”
“Yes, we’d do it again!”
Catch the
buzz on authorSTREAM
Copyright © 2002-2008 authorSTREAM. All rights reserved.