Presentation Transcript
MICE Target Development: MICE Target Development Chris Booth
Sheffield
8th June 2006
Slide2: Progress since last Collaboration Mtg.
Review of components
Assembly tests at RAL in April
Developments resulting from tests
Increased effort for target
Plans & schedule June to November
Components: Components Stator body
Ceramic tube
Glass readout tube
Target shuttle
Ceramic bearings
Electronics
Frame, jack, bellows, gate-valve
Stator (1): Stator (1) Stator body from Manchester not built to specs.
Micro-surgery allowed insertion of ceramic tube!
We have learned how to make all components for future stators in house.
Stator (2): Stator (2) Coil winding company provided satisfactory sample.
30 coils purchased, to construct new stator.
Coils wound in-house also satisfactory.
Will try new cooling and potting techniques in near future.
Ceramic tube: Ceramic tube Test flanges & dummy stator built at RAL.
Indium vacuum seals tested.
Pronounced satisfactory!
Optical readout enclosure: Optical readout enclosure Quartz glass tube and flange procured.
Flange machined, tube fixed with cryostat cement.
Shuttle: Shuttle Oxford assembled shaft, target, alignment fin, stop, magnets, readout vane (see picture) – many thanks!
Magnets, readout vane supplied by Sheffield.
For prototype, shaft produced from steel tube rather than titanium.
Assembly cleaned in Oxford, delivered direct to RAL.
Control electronics: Control electronics Cards now rack-mounted.
Extensive tests with prototype drive. Several hours pulsing at 0.3 Hz (10 A).
Some reliability & noise problems are being addressed.
Bellows: Bellows
Slide12: Indium seals Ceramic bearings
Slide13: Beam pipe Gate valve Bellows Drive mechanism Support frame
Assembly test: 24-28 April: Assembly test: 24-28 April First time many parts came together:
Stator first connected to electronics 20th
Glass readout tube assembled 21st
Target shuttle finished morning of 24th
Some RAL parts and flanges not previously assembled.
What did we learn?: What did we learn? Glass tube was very fragile!
Broken near metal flange.
Ground down and re-glued – vacuum tested ok.
New crack when tightened down onto full assembly.
Covered in epoxy! Amazingly, this appeared to seal ok!
Slide16: Target shuttle was distorted
Slot cut along thin-walled tube to take alignment vane caused shaft to distort.
Vane was twisted and slightly off-axis at one end.
Would not pass through ceramic bearing.
Slot & hole in bearing machined out to allow shaft and vane to pass.
Some play and roughness, but movement satisfactory.
Slide17: Titanium target Steel shaft Alignment fin Stop Magnets Optical readout vane
Slide18: Indium seals did not work!
Despite success with test pieces, could not pump down below 310–3 mbar.
Flanges found to have too large diameter and chamfer; rebates incorrect so inadequate closure of seal.
Attempts to seal with extra indium.
Only partial improvement.
Prevented vacuum quality checks with mass spectrometer.
Slide19: Temperature sensitivity
Operation of drive (power-off to hold position) caused deterioration in vacuum. (Only 10-15°C temperature rise.)
Chilled water cooling (12°C) also worsened vacuum.
Partial recovery on return to ambient temperature.
Movement of ceramic tube disturbing (imperfect) seal?
Slide20: Optical readout block did not fit
Insufficient space for readout block around glass tube when drive in raised position.
Large guide flange removed – appears not to be necessary.
Flange could also be machined down to allow space.
Slide21: Large flange
Slide22: Extremely difficult to align optics
Higher refractive index of quartz tube?
RAL restrictions on use of laser in hall.
Adjustment system not suitable for 3D alignment in both position and angle
Shaft length checked - OK
relative positions of target (raised) & gate valve, target (lowered) & beam-pipe, readout vane & top of tube etc were all correct.
Solutions to problems: Solutions to problems 1 & 6 Delicate glass tube, difficult alignment
Replace glass tube with steel plus flat glass windows
Robust, much simpler optics.
Redesign optical mounts to allow off-line alignment and accurate relocation.
Involve RAL engineer in design (in conjunction with Richard Nicholson).
Meeting yesterday in Sheffield.
Slide24: 2 Distorted shuttle shaft
Oxford redesigned target shuttle
Target, shaft, stop, alignment fin machined out of single piece of titanium.
Cross-shaped (or square?) cross-section.
Strong, no tendency to twist.
Only magnets and readout fin to be added.
New (or modified) ceramic bearings will be required – design to allow insertion of shaft through lower bearing for easier assembly.
Some questions have just arisen as to whether the shaft can be machined to this design! The design is under review.
Slide25: 3 & 4 Leaks at indium seals
Flanges for indium seals to be re-ground or re-made
Vacuum and temperature tests are being performed at RAL.
Importance of careful quality control
Vacuum & temperature cycling tests will also be performed in Sheffield
In longer term, consider need for bonded ceramic-metal.
Conclusions of Tests: Conclusions of Tests Despite problems, a lot was learned.
Practical details of assembly for first time.
Improved design of major components.
No proper vacuum tests.
No reliability or vibration tests.
Review held (with ISIS) 16th May.
Will repeat assembly in hall in July, full mechanical & electrical test in September.
Will not install in ISIS for June – perform thorough off-line checks for October access.
Increased Effort for Target Work: Increased Effort for Target Work Daresbury lab electronic engineer (Steve Griffiths)
High power driver electronics
Capacitor bank power supply
>100 A hex bridge using IGBTs
Oxford workshop effort
Shuttle shaft construction
Mechanical engineer (Martin Baldwin) (RAL)
Replacement chamber with optical windows
Readout alignment mounting (with RN at Sheff.)
Sheffield Physicist/Engineer (advertise soon!)
Thermal modelling of stator – improved cooling
Electromagnetic modelling – more efficient drive?
Slide28: Plans & Schedule (1)
Indium seal tests (RAL)
Build new shaft (Oxford)
Design/build top chamber/readout (Sheff/RAL)
Build new stator (Sheffield)
Vacuum tests (Sheffield)
Optical isolation of control boards (Sheffield)
Optical drive of hex bridge (Sheffield)
Improved control & monitoring (Sheffield)
Acceleration & temperature tests (in vacuum) (Sheffield)
Reliability tests (Sheffield)
Mechanical test at RAL 17th-21st July
Slide29: Plans & Schedule (2)
Build & test IGBT hex bridge driver (Daresbury)
Build second shaft (Oxford)
Build second (improved?) stator (Sheffield)
Build second top chamber/readout (Sheff/RAL)
New quadrature board for optics (Sheffield)
Improved controller hardware & software (Sheffield)
ISIS interface boards (Sheffield)
Temperature monitoring hardware & s/w (Sheffield)
Acceleration tests (at 80 A) (Sheffield)
Temperature, reliability tests (at 80 A) (Sheffield)
Mechanical & electrical test at RAL 18th-22nd September
Installation in ISIS October