Presentation Transcript
London Underground PPP :London Underground PPP 7 January 2003
Contents :2 Contents The Tube Lines Consortium and the project to manage the Jubilee, Northern and Piccadilly lines
1. What is the project? - The contract
- The consortium
- The inheritance
- Tube Lines’ responsibilities
2. How is the project structured and financed?
- Financial and commercial structure
- Risk assessment
3. Benefits to Jarvis
1. What is the project? :1. What is the project?
The contract :4 The contract 30 year project to own, manage and upgrade the infrastructure on the Jubilee, Northern and Piccadilly Lines (trains, track, signalling, stations)
Equal shares in Tube Lines Holdings Ltd between Bechteland Jarvis. Amey can accede by 30th June 2003 to becomea one-third partner
Total programme for first 7.5 years is £4.4bn, of which Opex is £1.5bn. Whole life programme of £14.8bn, of which £6.1bn is Opex
Bechtel responsible for Capex. Jarvis and Amey equally responsible for Opex. (If Amey does not accede, then Jarvis 75%, Bechtel 25%)
Tube Lines Consortium :5 Tube Lines Consortium Specialist skills in rail industry including:
Track and signal renewals
Project and operational management
Experience of successful metropolitan capital projects including:
Athens, Hong Kong, London, New York, San Francisco and South Korea
Experience in business services Three shareholders (Bechtel, Jarvis and Amey)who collectively provide: Flexibility retained on awarding supply contracts - clearly sponsors well qualified to benefit
Current status :6 Current status 1.75 million passengers per day (Monday-Friday)
Managed through some of the world’s busiest stations
Waterloo 32.6m people per year
Leicester Square 28.1m people per year
Tottenham Court Road 28.0m people per year
Our passengers are carried on 251 trains callingat 129 stations of which we maintain 101
Our trains do around 19m miles of track journeys per year
2,500 Total staff
Tube Lines’ assets :7 Tube Lines’ assets Trains 251
Stations 101
Escalators 220
Lifts 65
Deep Tunnels 98 miles
Total Track 212 miles
Performance regime :8 Performance regime Four measures of performance
Capex
Capability
Throughput of trains on the network measured in minutes per journey
Opex
Availability
Disruptions to operations measured in Lost Customer Hours (LCH’s)
Ambience
Look and feel of the stations and trains measuredin Mystery Shopper Survey (MSS) points
Service points
Ability to rectify non critical failures measured in points Benchmarks/thresholds set taking account of historic performance
Opex – recent performance :9 Opex – recent performance Availability - ahead of contract target
Service points - ahead of contract target
Ambience - 5% behind contract target - issue is cleanliness of Piccadilly line trains - detailed programme in place
First 7.5 years :10 First 7.5 years Major upgrade to the Jubilee Line (2009)
Major upgrade to the Northern Line (2011)
Station modernisation (30)
Station refurbishment (67)
Lift refurbishment (65)
Escalator refurbishment (80) Escalator replacement (48)
60 miles of track will be refurbished
42 miles of track will be renewed
31 Bridges repaired or strengthened
7 miles of earth structures upgraded
11 miles of drainage repaired
Service capacity :11 Service capacity 0 5 10 15 20 25 Piccadilly Line upgrade completed in 2nd 7.5 year period % increase in capacity Northern Line Jubilee Line Piccadilly Line By 2011 By 2009 By 2014
Improving reliability :12 Reducing Lost Customer Hours by 2010 Northern Line Improving reliability Jubilee Line Piccadilly Line 34% 15% 3% 0 10 20 30 40
Building a safer system :13 Building a safer system Replacing 42 miles of track
Refurbishing 60 miles of track
Introducing a new technology solution to monitor track condition
Re-signalling the Jubilee and Northern lines with modern, safe, reliable and proven systems miles
Creating a better environment :14 Creating a better environment Increasing personal security by covering the entire network with CCTV cameras
Easing station congestion by improving and replacing escalators and lifts
Upgrading 97 of our 101 stations, including new passenger help points, better information systems and new fire protection systems
Tripling capital investment :15 In the first seven and a half years: Tripling capital investment £750m is to be spent on signalling and trains
£580m is to be spent on betterand safer stations
£230m is to be spent on track replacement and refurbishment
LUL/TfL’s responsibilities :16 LUL/TfL’s responsibilities In summary, while Tube Lines is responsible forthe infrastructure, LUL is responsible for the trainoperations, specifically: Strategy and management of the tube network
Setting the priorities for modernisation
The operation of train services
The safety regime
Employment of some 8,000 employees across the network, including all drivers, customer-facing station staff and signalling control staff
Any closures of lines and stations for work to be done
Ticketing and fares
The timetables
The zone structure
2. How is the project structured and financed? :2. How is the project structured and financed?
Slide 18 :18 Jarvis Amey Bechtel Initial financial and commercial structure of project Opex management agreement Capex management agreement 50% 50% Equity BridgeLoan LUL ServiceContract Note:
If Amey accedes by 30th June 2003, it will become a 1/3 partner in Tube Lines and 50:50 partner with Jarvis in Opex JV Tube Lines (Holdings) Limited Tube Lines Limited Mezzanine Bank debt 100%
Slide 19 :19 Project structure if Amey does not accede 50% 50% 75% 25% Opex management agreement Capex management agreement Equity BridgeLoan LUL ServiceContract Tube Lines (Holdings) Limited Tube Lines Limited Jarvis Bechtel 100% Mezzanine Bank debt
Capital structure :20 Capital structure
Jarvis financial commitment (£90m) :21 Jarvis financial commitment (£90m) Initial share of investment
ordinary shares £22.5m
loan notes £45.0m £67.5m
Funded by Equity Bridge Loan of £67.5m to Tube Lines Holdings(repayable after 5 years)
Contingent equity commitment of a further £22.5m
The total of £90m is covered by letters of credit procured by Jarvis
If Amey accedes, the above amounts reduce by one third
Asset condition :22 Asset condition As contract is output-based, Tube Lines does assumeasset condition risk
Very substantial due diligence performed (since 1999), using site inspections and desk top analysis
Numerous independent consultants intimately involved in the process
LUL grouped assets into five classes and set requirements for proportions of assets to be moved up the hierarchy
Protection for catastrophic events, eg tunnel collapse and terrorism
Contractual protection :23 Contractual protection Comprehensive service contract, with flexibility for LUL to amend requirements at periodic review
Substantial protection achieved via entrenching key provisions
Independent role of Statutory Arbiter(who is a highly respected utility company regulator, Chris Bolt)
Statutory Arbiter must maintain the ISC profile that achieved the agreed IRR on the initial equity funding
Transport for London
Expected to work constructively now project has begun
Protection against risks of legal challenges
No transfer to TfL until challenge periods elapse
Contingent funding :24 Contingent funding Approved budgets for Capex, Opex and Tube Lines include contingencies which are covered by the project funding
Seconding parties are significantly incentivised to avoid overruns
Standby funding of £300m in place
If standby funding utilised, LUL bound to provide more revenue or reduce obligations, providing Tube Lines conformed to good industry practice
No obligation on sponsors to provide any further financial support
Summary :25 Summary Initial structure 50/50 Jarvis and Bechtel
Amey may accede by 30 June 2003
Jarvis equity commitment capped
Comprehensive knowledge of assets
Strong contractual protection
Robust funding structure
3. Benefits to Jarvis :3. Benefits to Jarvis
Strategic rationale :27 Strategic rationale Natural extension of existing rail business/expertiseinto London subway
Widens client base
Creates opportunities for winning futureoutsourcing contracts
Step increase in turnover and profits for Jarvis Group
Relevant Jarvis expertise :28 Relevant Jarvis expertise Leading UK rail infrastructure services provider
Introduction of Jarvis control centre technology:
Fault reporting
Response management
Staff location
CCTV technology - trains, depots, stations
On track machine management and innovation
Avonwood technology - rail flaw detection
Premises management - hard and soft fm Introduction of focused Jarvis management techniques
Widening Jarvis’ client base :29 1998 2002 2004(E) 63% 49% 37% 2004 (E) Based on house brokers’ forecasts Widening Jarvis’ client base Network Rail Other Network Rail revenue as a percentage of total revenue
Outsourcing contract opportunities :30 Outsourcing contract opportunities Tube Lines is committed to competitively tendering alloutsourced works
Jarvis expects to compete for:-
Track renewals - £230m in first 7.5 years
Signalling – installation and maintenance role for conventional systems
Track maintenance
Facilities management - station and engineering depots, fabric maintenanceand soft services
IT - Agilisys are working on new management information systems
Sources of revenue and profit – Jarvis :31 Sources of revenue and profit – Jarvis
Management Agreement :32 Management Agreement Management agreement to support delivery of the Opex programme to defined budgets
Expertise and intellectual capital
Provision of senior managers on full time secondment
Fees include incentives to reduce costs - gain/pain share
Annual gross revenue – approximately £8m* * Assumes a 1/3 share
Equity returns :33 Equity returns Consolidation of share of TLH group* revenue and profits
Operating return from Tube Lines Limited (but no dividends expected in first 7½ year period)
Investment servicing cost covered by project:
Interest income from Tube Lines Limited enables TLH to service EBL and mezzanine
LC costs largely recovered * Comprises TLH and Tube Lines Limited
P & L impact on Jarvis :34 Year to 31 March 2004 (F)
No material impact on year to 31 March 2003(except JV turnover of approximately £45m)
Ignores any outsourced work
Assumes a 1/3rd share P & L impact on Jarvis
Cash flow and funding impact on Jarvis :35 Cash flow and funding impact on Jarvis Cash Flow
Bid costs recovered on financial close
Management fees
Funding
Committed equity funded by equity bridge loan into TLH
Committed and contingent equity supported by letters of credit (LC) from Jarvis bankers
LC facilities supported by cash collateral
£20m on day 1
Progressively thereafter out of project cash flow
Summary :36 Summary Exciting opportunity for Jarvis – well suited toour experience
Significant revenues and widening of client base
Substantial expected profits and cash flow
Upside potential
Opportunities for outsourced work in track work, signalling, facilities management and IT
London Underground PPP :London Underground PPP 7 January 2003
Catch the
buzz on authorSTREAM
Copyright © 2002-2008 authorSTREAM. All rights reserved.