Presentation Transcript
Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective: Transformer Tank Rupture and Mitigation – Hydro-Québec Perspective Marc Foata and Van Nhi Nguyen
TransÉnergie Une division d'Hydro-Québec
Background: Background Early 1980s, increasing number of catastrophic failures on our 735 kV system
Two major blackouts
Safety threats to the workers
Environment concerns due to oil spills and fire
Background: Background 1984- 1987: Study works of HQ - ABB joint teams many measures implemented; among these measures:
Welded cover instead of bolted type
Physical separation of radiators and conservator from main tank and with devices to prevent oil spilling in case of pipe rupture
Modifications to tank reinforcement beams
Fire extinguishing walls and oil retention basin
AND most importantly higher test levels for more reliable performances and larger margin in insulation
Background: Background 1987-1992 Major R&D project on arc-induced explosion and tank ruptures
1992 New requirement in Hydro-Québec specifications, no minimum level is enforced but question must be adressed during the design review
1992-1993 Joint effort with ABB for a more resistant tank design
1992-2006 All our transformer suppliers have demonstrated adequate ability to take into account this new requirement in their analysis
Mitigation approaches: Mitigation approaches Protection: Improve fault interruption delay so that very low energy is released
Insulation: Correct all design weaknesses so that no fault can occur
Containment: Make a pressure resistant tank that can safely withstand or evacuate all energy levels
Results: Results Protection: 3.5 cycles average fault interruption time, reduced to less than 3 cycles
Insulation: Several weaknesses have been identified and corrected. Yet the possibility of a major fault could not be totally discarded
Containment: Very little knowledge on the subject, a R&D project is initiated
Failure statistics 735 kV (25 years): Failure statistics 735 kV (25 years) 175 failures that resulted in 111 high energy arcs causing 44 tank ruptures and finally 18 fires
Rupture vs Fault Energy 700 kV: Rupture vs Fault Energy 700 kV
"Worst" worst rupture modes: "Worst" worst rupture modes
"Less" worst rupture mode: "Less" worst rupture mode
"Least" worst rupture mode: "Least" worst rupture mode
R&D Simulation tools: R&D Simulation tools Theoretical part based on analytical and numerical models identifying fundamental parameters. Derive a straightforward method for calculating the static pressure.
R&D Arc simulation setup: R&D Arc simulation setup Experimental part involving simulation of the dynamic load factor F to be applied to the static pressure to take into account the dynamic effects.
R&D Results: R&D Results Pressure Displacement
R&D Results & Conclusions: R&D Results & Conclusions Arc induced explosions can be simulated but sophisticated tools are required
Deformation, not pressure, should be used to determine tank rupture.
Dynamic factor have been proposed to extrapolate static calculations
Testing by high pressure gas injection is possible
New tank resistance specification has been formulated
New specifications - Philosophy: New specifications - Philosophy Priority is given to the protection of the workers
Worst energy levels may not always be containable by the tank
First rupture point must be the cover
Required calculation tools must be accessible to transformer designers
Must take into account the highly dynamic phenomena involved
Must be easily verified
New specifications - Objectives: New specifications - Objectives Stimulate new tank designs
Exchange technical information with manufacturers
Aiming in long term to see that new tank designs meet arc energy requirements
New specifications - Formula: New specifications - Formula Ps – Calculated tank pressure withstand
F – Dynamic (time & location) amplification
E – Fault energy level to withstand
K – Arc energy conversion factor
C – Tank expansion coefficient
New specifications – Dynamic factor: New specifications – Dynamic factor Time related dynamic factor (pressure and deformation)
Proximity related dynamic factor
Takes into account tank volume
Manufacturers' response: Manufacturers' response All transformer suppliers since 1992 have shown adequate tank withstand analysis
One supplier has proposed an improved tank design (double arc containment capability to 20 MJ)
Containement of the highest levels of arc energy require complicated pressure venting system with numerous rupture disk all over the tank or double-walled tanks
Where do we go from here ?: Where do we go from here ? Present design can contain up to 10 MJ for the largest tanks (735 kV)
More resistant tank design can be achieved
Need to implement specifications with minimum energy requirement to meet . Utilities need to agree on reasonable levels
Testing by high pressure gas injection is feasible and more appealing than real arc testing