Downtown Action Team A Progress Report Roger Storey, Deputy City Manager Coordinator April 15, 2003

COUNCIL GOAL: 

COUNCIL GOAL Revitalize Downtown andamp; The Waterfront

Slide3: 

Planning for street and parking security and hospitality when cinema opens Aggressive Solicitation 'Panhandling' Ordinance in effect Police And Corrections Team (PACT) continues to reduce parolee recidivism Pay Phone Ordinance to address nuisance pay phones to Council soon

Slide4: 

SJRRC renovating historic Southern Pacific Depot; completion by October SJRTD construction of Downtown Transit Center to begin by summer COG: 30,000 sq. ft. 3-story office building, northwest corner of American and Weber; completion by October County administration and Superior Court facilities

Slide5: 

Bank of Agriculture and Commerce — renovation / new facade / reuse of three buildings; start spring ‘04 Marina Tower-- Barry Swenson Builder / County negotiations expected to conclude soon Builders Exchange and State office buildings on South Shore -- discussions underway

Slide6: 

10-20 cottage-style single-family units east of Fremont Park Gleason Park Housing DDA with Housing Development andamp; Neighborhood Preservation Corp. of San Francisco to Council by late summer 16 cottage-style single-family homes north of park by ACLC, construction fall 2003 Mercy Charities Phase I -- 56 units family housing and child care center in block northeast of park SUSD elementary school south of park

Slide7: 

Renovation of Fox Theater in progress; completion expected early 2004 Weber Point Grill? Downtown Retail Strategy drafted; presented to DAT Stockton Stroller trolleys roll on; DAT helping increase ridership

Slide8: 

'The Stockton' restoration underway!!! Cineplex construction underway!!! 16 screens, 3,400 seats, 18,000 sq. ft. retail, foundation within several weeks 96 studio and 60 one-bedroom units of senior housing 25,000 sq. ft. retail

WATERFRONT WEST : 

WATERFRONT WEST Baseball Stadium Spanos apartments Grupe mixed-use neighborhoods Arena Hotel

Slide10: 

Discussing draft design guidelines for Downtown Lighted mid-block crosswalk on El Dorado at Main Weber Avenue Streetscape project complete; Main St. improvements underway Urban Design, Historic Preservation, Infrastructure Exploring need for infrastructure upgrades in downtown, including sidewalks Old signs and newspaper racks

Slide11: 

Downtown Action Team A Progress Report Roger Storey, Deputy City Manager Coordinator January 14, 2003