Progress in Establishing an Underground Lab at Homestake: Kevin T. Lesko
for the Homestake Collaboration
Lawrence Berkeley National Lab
Institute for Nuclear and Particle Astrophysics Progress in Establishing an Underground Lab at Homestake Many more details giving at Joe Wang’s lecture series
Homestake Exec: Milind Diwan - BNL
Ken Lande - Penn
Bob Lanou - Brown
Hitoshi Murayama - UCB
Bill Roggenthen - SDSMT
Joe Wang - LBNL
Herb Wang - UW
Dave Snyder - SDSTA Homestake Exec
Challenges and Opportunities for Homestake & DUSEL: Common to many sites
The Site
Depth
Title
Environmental and Permitting
Water
Science & Time Scale Challenges and Opportunities for Homestake & DUSEL
Goals: Low risk and Safe
Follow the Science
Break the chicken-egg cycle -- need experiments but need a site first
Excellent State Support
Comprehensive site
Cost Effective
Complementary Roles - Science and State Goals
Slide5: Expedient access to ~20 cubic kilometers of rock mass, depths to 4850 feet, many existing spaces and excavations suited for science in the near term 4850 Laboratory open by 2007
Evolving Campus with PDK: Evolving Campus with PDK UNO Detector Early Clean Campus Later Clean Campus Later Dirty Campus Early Dirty Campus
Depth: Near term access from surface to 4850 feet below ground by 2007
Re-establish access to > 8000 feet as part of the DUSEL process ~ 2009
Many rooms available on this time scale to be adapted for stationary experiments
~ 60 levels available from surface to 8000 for extended earth science investigations Depth
Early Implementation Plan: To preserve Homestake for DUSEL need to address water, title, access.
Plan was established and vetted last year to:
obtain title to the facility
regain access to the facility
deal with the water (upper water immediately ~ 2/3 of the 700 g/min), ensure lower water
refurbish lifts and shafts (Ross and Yates)
establish an interim facility at 4850 and above start science early!
establish a plan for growth into a national facility Early Implementation Plan
Title: Barrick and South Dakota agreed to the transfer of the property in January 2004, in Feb. 2005 this was expanded to include the 4850 “early lab”
SDSTA, Barrick and the State Government (Governor’s office) are in the final stages of the process to implement the transfer and to amend the “Agreement in Principle” to suit the 4850 lab
Governor’s Office is enthusiastic & anxious to pursue state funding sources as soon as the “Agreement” is completed
Process should reach closure according the original schedule - title expected to be secured by October 2005 Title
Permitting and EPA: Water discharge permits have been obtained, extension of the current permits obtained by Barrick and transfered to SDSTA
Mine closure plan vetted by EPA several years ago, including site inspections Permitting and EPA
Water: Not uncommon to have water of this magnitude in a mine, 2/3 from the surface
Cycles of Flooding and dewatering are not uncommon
Water quality not likely to significantly degrade the infrastructure (pH neutral water)
Important to preserve the 4850 level
Implementation plan deals with this Water
Water: Pumps shut off in ~ May 2003
6800 level was crossed Nov 2004 ~ month behind expectations
6200 has not yet been crossed
Expected to cross 4850 late 2007-early 2008, if nothing is done in the mean time Water
Time Line: TABLE 1 Homestake DUSEL Laboratory Development Schedule. Items marked with ✓ have been completed ✓ January 12, 2004 ТAgreement in PrincipleУ between Barrick and SDSTA to transfer mine. ✓ February 11 2004 Legislature passes necessary enabling and appropriation legislation to effectuate transfer and provisions in the Agreement in Principle. ✓ July 2004 State funds $14.3M to enable site transfer and operate SDSTA ✓ February 1, 2005 SDSTA Board approves development of fiscal and management plan (Implementation Plan) for 4850 level laboratory ✓ February 16, 2005 Barrick confirms establishment of the 4850 level laboratory satisfies the definition of laboratory in the Agreement in Principle ✓ February 25, 2005 SDSTA initiates application for a water discharge permits with the South Dakota Department of Environmental and Natural Resources (DENR) ✓ February 28, 2005 Submission of Homestake S-2 Response to the NSF May 15, 2005 4850 level Laboratory Implementation Plan submitted to the SDSTA Board June 15, 2005 Implementation Plan accepted by SDSTA, State of South Dakota and Barrick. June 15, 2005 Request for Letters of Interest July 15, 2005 Funds for the 4850 level laboratory access are secured August 25, 2005 DENR Water discharge permits received by the SDSTA August 2005 Review of S-2 submission. 1st round of workshops gathering experimental requirements and criteria for the science and education and outreach programs October 1, 2005 Transfer of the Homestake site from Barrick to SDSTA completed October 1, 2005 Begin work on site rehabilitation and the 4850 level laboratory access January 1, 2006 2nd round of workshops defining engineering plan for Scientific Programs, Education and Outreach and Deep Lab Development May 1, 2006 4850 level ready for construction of new experimental chambers and/or occupancy of existing chambers November 1 2006 Complete modifications to existing underground 4850 space and begin experiments Time Line
Progress: TABLE 1 Homestake DUSEL Laboratory Development Schedule. Items marked with ✓ have been completed ✓ January 12, 2004 ТAgreement in PrincipleУ between Barrick and SDSTA to transfer mine. ✓ February 11 2004 Legislature passes necessary enabling and appropriation legislation to effectuate transfer and provisions in the Agreement in Principle. ✓ July 2004 State funds $14.3M to enable site transfer and operate SDSTA ✓ February 1, 2005 SDSTA Board approves development of fiscal and management plan (Implementation Plan) for 4850 level laboratory ✓ February 16, 2005 Barrick confirms establishment of the 4850 level laboratory satisfies the definition of laboratory in the Agreement in Principle ** this is key, but required some work on the “Agreement” ✓ February 25, 2005 SDSTA initiates application for a water discharge permits with the South Dakota Department of Environmental and Natural Resources (DENR) ✓ February 28, 2005 Submission of Homestake S-2 Response to the NSF ✓ May 15, 2005 4850 level Laboratory Implementation Plan submitted to the SDSTA Board June 15, 2005 Implementation Plan accepted by SDSTA, State of South Dakota and Barrick. June 15, 2005 Request for Letters of Interest July 15, 2005 Funds for the 4850 level laboratory access are secured ✓ August 25, 2005 DENR Water discharge permits received by the SDSTA ✓ August 2005 Review of S-2 submission. 1st round of workshops gathering experimental requirements and criteria for the science and education and outreach programs October 1, 2005 Transfer of the Homestake site from Barrick to SDSTA completed October 1, 2005 Begin work on site rehabilitation and the 4850 level laboratory access January 1, 2006 2nd round of workshops defining engineering plan for Scientific Programs, Education and Outreach and Deep Lab Development May 1, 2006 4850 level ready for construction of new experimental chambers and/or occupancy of existing chambers November 1 2006 Complete modifications to existing underground 4850 space and begin experiments Progress Iterations and refinement }
Slide15: ✓ February 28, 2005 Submission of Homestake S-2 Response to the NSF ✓ May 15, 2005 4850 level Laboratory Implementation Plan submitted to the SDSTA Board June 15, 2005 Implementation Plan accepted by SDSTA, State of South Dakota and Barrick ** in progress and nearing completion (final review) ** June 15, 2005 Request for Letters of Interest ** probably August or Sept, now for the first call for LOIs ** July 15, 2005 Funds for the 4850 level laboratory access are secured ** state is poised to proceed as soon as title is obtained ** ✓ August 25, 2005 DENR Water discharge permits received by the SDSTA ✓ August 2005 Review of S-2 submission. 1st round of workshops gathering experimental requirements and criteria for the science and education and outreach programs **Workshop in September/October 2005** October 1, 2005 Transfer of the Homestake site from Barrick to SDSTA completed ** still a valid date, assuming final site surveys are completed on time ** October 1, 2005 Begin work on site rehabilitation and the 4850 level laboratory access ** delay until spring, with small or little affect on opening date ** (not working in winter, increase state, complete plans, competitive bid the plans) January 1, 2006 2nd round of workshops defining engineering plans for Science, E & O May 1, 2006 4850 level ready for construction of new chambers, occupancy existing chambers ** 2nd 1/2 2006 November 1 2006 Complete modifications to existing space and begin experiments ** early 2007**
Focus of S-2: Build nation-wide support for Underground
Workshops to assess the needs, timeline, requirements of science and E&O
Request near-term and long term LOIs
Develop and “engineer” science and education program
Develop concept for deep lab and expansion of Homestake Focus of S-2
Plan of 4850 level: Plan of 4850 level Existing Space at 4850 for:
Prototyping
Low Background Labs
Nuclear Astrophysics
Who Can Use it?: Who Can Use it? Near Term:
Surface to 4850 hydrology, geology, geochemistry
Rock deformation studies using drifts and shafts
Studies of the cratonic crust through 20 km3
Searches for life and exotic biology including initial microbial investigations
Investigations of flow path delineation in heterogeneous geological settings & ground water studies/models
Characterizations of facture mapping, stress measurements and ground water chemistry
Thermal-mechanical-hydrological couplings across many orders of magnitude in scale
Longer Term:
Systematic searches for and characterizations of life
Long term and large scale characterizations and expts.
Carbon Sequestration Earth Science, Biology and Engineering
Who Can Use it?: Who Can Use it? Near Term:
Cosmic Rays Studies
Low Level Counting
Prototyping, Materials Production for
Double Beta Decay
Dark Matter
Next Generation Dark Matter
Next Generation Double Beta Decay
Nuclear Astrophysics
Begin work on Proton Decay & Long Baseline
Longer Term:
Continued operation of DM, DBD
Solar Neutrinos
CP violation Long Baseline
PDK
Supernovae monitors Physics Uses
Slide20: NB: to complete the rehabilitation, including complete dewatering, providing safe access to 8000 feet:
$50 M
15 month
Additional Room Construction:
Competitively priced, would use fraction of original hoisting capacity of the mine (7000 T/day)
Initial engineering studies support massive room construction feasible at 7400 level
Identified excavated rock disposal sites
Water permits initiated