Cisco Bike Path - BOS presentation

Views:
 
Category: Education
     
 

Presentation Description

Nantucket Planning Board Presentation to the Board of Selectman in regards to the Hummock Pond Road Bike Path. Oct 2011

Comments

Presentation Transcript

Hummock Pond Road Bike Path (a.k.a. Cisco Bike Path) Phase 1, 2, and 3 Implementation Strategy October 12, 2011: 

Hummock Pond Road Bike Path (a.k.a. Cisco Bike Path) Phase 1, 2, and 3 Implementation Strategy October 12, 2011

Slide 2: 

Phase 3

Slide 3: 

Bike path will run from end of Milk Street extension to Cisco Beach Funding from the Town of Nantucket and private donations Estimated completion date: Figawi Weekend 2013 Implements path six years earlier than Transportation Improvement Program funding Cisco Bike Path – Phase 1, 2, 3 Implementation Summary Phase 3

Slide 4: 

May 2013: - Construction complete October 2012: - Construction Starts August 2012: - Bid opening July 2012: - Construction bid May 2012: - Finalize all design plans April 2012: - Construction funding approval at ATM/ballot vote March 2012: - ROW secured/recorded via County taking February 2012: - County hearing of taking challenges January 4, 2012: - County public hearing for taking all easements December 2011: - Finalize ROW notices and documents - Conservation Commission review - Shadbush becomes de-listed November 2011: - ROW plan complete / initiate October 2011: - BOS / County approval of implementation strategy - Finalize amendment to design contract with VHB Cisco Bike Path Implementation Schedule

Slide 5: 

Cisco Bike Path – Right of Way (ROW) Issues Total Easement Area = 251,629 square feet (5.8 acres) from 37 property owners Goal : Secure right of way by April Town Meeting Voluntary donation of easements will be requested in December 39,431 sqft donated by Hummock Pond of Nantucket and 86,844 sqft to be donated by Nantucket Islands Land Bank May require an eminent domain taking and possible damage awards to property owners

Slide 6: 

Cisco Bike Path – Right of Way (ROW) Impacts Owner Easement Area (sqft) Nantucket Islands Land Bank 86,844 Hummock Pond of Nantucket 39,431 Cordelia C. Everett & Richard M. Everett III 27,846 Bartlett Farm, LLC 16,396 James Georgaklis, Trustee of the Hummock Pond Realty Trust 8,407 Kimberlee Johnson Morcom and Richard Evan Morcom 8,274 Stephen P. Cherner and Vickery Merry Cherner 6,318 Bruce Holdgate 5,580 Bette A Ferris 4,675 Gertrude Bernard, Trustee Bernard Realty Trust 4,115 Warren C. Pease 3,787 Frank H. Powers, Jr. & Beth L. Warner 3,585 James E. Cahill and Zelda B. Cahill 3,523 Stephen P. Cherner Trustee of PAC-RIM Realty Trust 3,217 Stephen P. Cherner, Trustee of Spotted Owl Realty Trust 3,080 Over 50% of Total Easement Area

Slide 7: 

Cisco Bike Path – Right of Way (ROW) Issues by Phases Phase # of Property Owners Easement Area Issues Phase 1 3 69,344 (needed: 24,670) Wetland and possible agricultural restriction issues Phase 2 23 47,376 (needed: 47,376) Private landscaping issues Phase 3 9 134,909 (needed: 53,308) Large tree and private landscaping Phase 3

Slide 8: 

Phase 1 Issues - Wetland Wetland near Millbrook Road intersection

Slide 9: 

Phase 2 Issues – Private landscaping

Slide 10: 

Phase 3 Issue – Private landscaping 166 Hummock Pond Road

Slide 11: 

Cisco Bike Path – Wetland Impacts Process would proceed concurrent with the right of way acquisitions Conservation Commission applications would need to be signed in cooperation with property owners Minimum 2:1 replication is required Wetland near Millbrook Road intersection

Slide 12: 

Description Unit Price Quantity Total Cost Full Depth Pavement Bike-path $81.50 /SY 14,667 SY $1,195,333.33 Full Depth Bike-path Over Drive $81.50 /SY 333.333 SY $27,166.67 Loam & Seed for Grading $12.50 /SY 17,600 SY $220,000.00 Drainage Swale $29.00 /SY 3,667 SY $106,333.33 Signing and Striping $20,000.00 /LS 1 LS $20,000.00 Block Wall $15.00 /SF 1,000 SF $15,000.00 Clearing & Grubbing $15,000.00 /AC 5.5 AC $82,500.00 Drainage Structures $3,000.00 /EA 66 EA $198,000.00 SUBTOTAL: $1,864,333.33 Cisco Bike Path – Cost Estimate Construction Staking ($1/ft) $13,200.00 Police Detail Say $10,000.00 Mobilization (3%) $55,930.00 Construction Traffic Management Say $5,000.00 Contingencies (25%) $466,083.33 Wetland Replication (approx.) $25,000 CONSTRUCTION COST TOTAL: $2,439,546.67* * - Does not include legally required easement damage awards