Automatic Farm Gate: 

Automatic Farm Gate INTEREGR 160 Instructor: Prof. John Murphy SA: Brandon Dudley December 12, 2006

Outline: 

Outline Background Problem Statement Gantt Chart Brainstorming Preliminary Designs Evaluation Integrated Design Construction & Materials Testing Budget Alternative Design Summary

Background Information: 

Background Information Mark Novak and AgrAbility Project America’s aging farming populations need labor-saving devices to assist their everyday task Currently, farm gate must be opened manually after exiting a vehicle Current products in the market are unsatisfactory (expensive and must be bought as a package with a new gate)

Problem Statement : 

Problem Statement Our goal is to design an automated gate to meet the needs of the aging and disabled farming population. The gate will be remotely opened and closed to reduce the amount of physical labor required to operate the gate. We will be providing the farmers with a safer, inexpensive, and reliable system that can be easily constructed and operated

Timeline – Gantt Chart: 

Timeline – Gantt Chart

Brainstorming – Small Group and Big Group: 

Brainstorming – Small Group and Big Group Sliding gate Swinging gate Drop down gate Flip down gate Lamborghini (pivot) gate Double swinging gate Wheeled gate Rotating gate Solar powered Pulley system Gear motored Screw drive powered Magnetic lock Ground switch Rechargeable battery Rotary powered Gates of fire

Brainstorming Continues…: 

Brainstorming Continues…

Preliminary Small Teams’ Design: 

Preliminary Small Teams’ Design Screw drive powered sliding gate Sliding gate powered by spring loaded wheels Rack and pinion sliding gate Geared power swinging gate

Evaluation Criteria: 

Evaluation Criteria Safety Durability Reliability Accessibility Simplicity Cost Time Serviceability Adaptability Manual Operation

Integrated Design & Prototype: 

Integrated Design & Prototype A swinging gate powered by a motorized wheel attached to the gate Motorized wheel bought from Tecel Spring loaded shock system attached to the wheel to accommodate rough terrains A solenoid powered latch ½ scale prototype (3 ft x 8 ft) Radio receiver and transmitter to apply power and switch direction of motor

Material & Budget Breakdown: 

Material & Budget Breakdown PVC’s (Home Depot) – Total: $27.63 5 - 10 ft, 1 inch PVC pipes 4 - 1 inch L connectors 8 – 1 inch T connectors 3 – 1 inch X connectors 2 Gate Hinges (Ace Hardware): $10 Gate attachment Support attachment 6 Bolts (3/8 inches course) 2 nuts (3/8 inches course) Nuts & Bolts (Ace Hardware): $18.17 4 guidance bolts 2 stabilizer bolts 1 threaded U bolt 8 nuts 8 washers 3 fine thread bolts

Material & Budget Breakdown cont.: 

Material & Budget Breakdown cont. Tubular Solenoid, Pull Type, 1.00” (25 mm) DIA X 2.00” (51 mm) L; 12 DC volts; continuous cycle (ElectroMechanicsOnline): $47.82 2 Channel Rolling Code RF Remote and Receiver (Car’s Electronics): $45.00 Continuous – Length Compression Springs (McMaster – Carr): $14.51 – UNUSED 2 Way Lockable Gate Latch (Northern Tool + Equipment): $27.53 – UNUSED Motorized Wheel 7 inches diameter (TECEL): $48.00 Radioshack Electrical Supplies: Total $22.96 2 DPDT 10Amp 12 VDC Relays ½ Amp Slow Blow Fuse 5 Amp Slow Blow Fuse 2 Kill Switches (Amazon.com): $9.98 – UNUSED Battery Latches assembly 1 – 1” washer 1/8” x ¼” x 4 3/8” metal bar Wheel Attachment Aseembly 3 metal plates 1 spring 2 inches diameter

Total Budget: 

Total Budget Total spent: $271. 60 Total used on prototype: $219.57 Theoretical budget for user: ~ $100.00 - $200.00* *Battery sold separately

Constructions : 

Constructions Order of materials PVC gate construction Spring loaded shock system construction Attachment of motorized wheel to the shock system Development of electrical details Development of latching mechanism Full assembly

Prototype: 

Prototype

Latch Design: 

Latch Design

Wheel’s Detail: 

Wheel’s Detail

Electronics: 

Electronics Powered by 12V automobile battery Two channel radio transmitter/receiver Radio signals activate relays, allowing current to power the motor and latch Signal 1 trips relay 1, allowing current to flow in one direction Signal 2 trips relay 2, allowing current to flow in the opposite direction

Design’s Advantages: 

Design’s Advantages Only simple modification needed to be done on the existing gate Less chances of physical injury (compared to gear or pulley system) Works in various terrains Can be manually opened in case of power outage Only require small power (enough to be powered by a battery)

Testing: 

Testing Preliminary computations to prevent later problems Testing on the remote control system Testing on the locking mechanism Testing on the strength of the wheel Testing on the shock system Testing power source and other electronic components

Alternative Design & Adaptation: 

Alternative Design & Adaptation Larger wheels will be needed for full-scale gate Improvement on the locking mechanism (stronger solenoid) Alternative spring loaded shock system (suspension system) Extensive weather and terrain factorization

Special Thanks To:: 

Special Thanks To: Prof. John Murphy Our SA: Brandon J. Dudley SA Amit Nimunkar Burke O’Neal Countless efforts of fellow team members COE Student Shop