Slide2: Commercial Industry (15)
Daimler Chrysler, Freshwater Partners, Galorath, Group Systems.Com, Hughes, IBM, Cost Xpert Group, Microsoft, Motorola, Price Systems, Rational, Reuters Consulting, Sun, Telcordia, Xerox
Aerospace Industry (6)
Boeing, Lockheed Martin, Northrop Grumman, Raytheon, SAIC, TRW
Government (8)
DARPA, DISA, FAA, NASA-Ames, NSF, OSD/ARA/SIS, US Army Research Labs, US Army TACOM
FFRDC’s and Consortia (4)
Aerospace, JPL, SEI, SPC
International (1)
Chung-Ang U. (Korea) Acknowledgments: USC-CSE Affiliates
Software Engineering Trends: Software Engineering Trends
Large-System Example: Future Combat Systems: From This... Large-System Example: Future Combat Systems
Slide5: Total Collaborative Effort to Support FCS
Slide6: FCS Product/Process Interoperability Challenge
Small-Systems Example: eCommerce: Small-Systems Example: eCommerce Lines of readiness
Are we ready for the next step? Iteration
Scope, Listening, Delivery focus Identify System Actors Document Business Processes Generate Use Cases Define basic development strategies Object Domain Modeling Detailed Object Design, Logical Data Model Object Interactions, System Services Polish Design, Build Plan Build 1 Build 2 Stabilization Build Release to Test Beta Program Pilot Program Production 16-24 week fixed schedule LA SPIN
Copyright © 2001 C-bridge
Future Software/Systems Challenges: Future Software/Systems Challenges Distribution, mobility, autonomy
Systems of systems, networks of networks, agents of agents
Group-oriented user interfaces
Nonstop adaptation and upgrades
Synchronizing many independent evolving systems
Hybrid, dynamic, evolving architectures
Complex adaptive systems behavior
Complex Adaptive Systems Characteristics: Complex Adaptive Systems Characteristics Order is not imposed; it emerges (Kauffman)
Viability determined by adaptation rules
Too inflexible: gridlock
Too flexible: chaos
Equilibrium determined by “fitness landscape”
A function assigning values to system states
Adaptation yields better outcomes then optimization
Software approaches: Agile Methods
Getting the Best from Agile Methods: Getting the Best from Agile Methods Representative agile methods
The Agile Manifesto
The planning spectrum
Relations to Software CMM and CMMI
Agile and plan-driven home grounds
How much planning is enough?
Risk-driven hybrid approaches
Leading Agile Methods: Leading Agile Methods Adaptive Software Development (ASD)
Agile Modeling
Crystal methods
Dynamic System Development Methodology (DSDM)
* eXtreme Programming (XP)
Feature Driven Development
Lean Development
Scrum
XP: The 12 Practices: XP: The 12 Practices The Planning Game
Small Releases
Metaphor
Simple Design
Testing
Refactoring Pair Programming
Collective Ownership
Continuous Integration
40-hour Week
On-site Customer
Coding Standards -Used generatively, not imperatively
The Agile Manifesto: The Agile Manifesto Individuals and interactions over processes and tools
Working software over comprehensive documentation
Customer collaboration over contract negotiation
Responding to change over following a plan We are uncovering better ways of developing
software by doing it and helping others do it.
Through this work we have come to value: That is, while there is value in the items on the right, we value the items on the left more.
Counterpoint: A Skeptical View Letter to Computer, Steven Rakitin, Dec. 2000: Counterpoint: A Skeptical View Letter to Computer, Steven Rakitin, Dec. 2000 “customer collaboration over contract negotiation”
Translation: Let's not spend time haggling over the details, it only interferes with our ability to spend all our time coding. We’ll work out the kinks once we deliver something...
“responding to change over following a plan”
Translation: Following a plan implies we would have to spend time thinking about the problem and how we might actually solve it. Why would we want to do that when we could be coding?
The Planning Spectrum: The Planning Spectrum Hackers XP Adaptive
SW Devel. Milestone
Risk- Driven
Models … … Milestone
Plan-Driven
Models Inch- Pebble
Micro-milestones,
Ironbound
Contract Software CMM Agile Methods CMMI
Agile and Plan-Driven Home Grounds: Agile and Plan-Driven Home Grounds
Agile Home Ground Plan-Driven Home Ground
Slide17: How Much Planning Is Enough? - A risk analysis approach Risk Exposure RE = Prob (Loss) * Size (Loss)
“Loss” – financial; reputation; future prospects, …
For multiple sources of loss:
Slide18: Example RE Profile: Planning Detail - Loss due to inadequate plans Time and Effort Invested in plans RE =
P(L) * S(L) high P(L): inadequate plans
high S(L): major problems
(oversights, delays, rework) low P(L): thorough plans
low S(L): minor problems
Slide19: Example RE Profile: Planning Detail
- Loss due to inadequate plans - Loss due to market share erosion Time and Effort Invested in Plans RE =
P(L) * S(L) low P(L): few plan delays
low S(L): early value capture high P(L): plan
breakage, delay
high S(L): value
capture delays
high P(L): inadequate plans
high S(L): major problems
(oversights, delays, rework)) low P(L): thorough plans
low S(L): minor problems
Slide20: low P(L): thorough plans
low S(L): minor problems
Example RE Profile: Planning Detail - Sum of Risk Exposures Time and Effort Invested in Plans RE = P(L) * S(L) low P(L): few plan delays
low S(L): early value capture high P(L): plan
breakage, delay
high S(L): value
capture delays Sweet Spot high P(L): inadequate plans
high S(L): major problems
(oversights, delays, rework)
Slide21: Comparative RE Profile:
Plan-Driven Home Ground Time and Effort Invested in Plans RE = P(L) * S(L) Mainstream
Sweet
Spot Higher S(L):
large system rework Plan-Driven Sweet Spot
Slide22: Comparative RE Profile:
Agile Home Ground Time and Effort Invested in Plans RE =P(L) * S(L) Mainstream Sweet Spot Lower S(L): easy rework Agile Sweet Spot
Conclusions: CMMI and Agile Methods: Conclusions: CMMI and Agile Methods Agile and plan-driven methods have best-fit home grounds
Increasing pace of change requires more agility
Risk considerations help balance agility and planning
Risk-driven “How much planning is enough?”
Risk-driven agile/plan-driven hybrid methods available
Adaptive Software Development, RUP, MBASE, CeBASE Method
Explored at USC-CSE Affiliates’ Executive Workshop, March 12-14
CMMI provides enabling criteria for hybrid methods
Risk Management, Integrated Teaming
Software Engineering Trends: Software Engineering Trends
Slide25: Getting the Best from COTS COTS Software: A Behavioral Definition
COTS Empirical Hypotheses: Top-10 List
COTS Best Practice Implications
COTS-Based Systems (CBS) Challenges
Slide26: COTS Software: A Behavioral Definition Commercially sold and supported
Avoids expensive development and support
No access to source code
Special case: commercial open-source
Vendor controls evolution
Vendor motivation to add, evolve features
No vendor guarantees
Of dependability, interoperability, continuity, …
Slide27: COTS Top-10 Empirical Hypotheses-I Over 99% of all executing computer instructions come from COTS
Each has passed a market test for value
More than half of large-COTS-product features go unused
New COTS release frequency averages 8-9 months
Average of 3 releases before becoming unsupported
CBS life-cycle effort can scale as high as N2
N = # of independent COTS products in a system
CBS post-deployment costs exceed development costs
Except for short-lifetime systems - Basili & Boehm, Computer, May 2001, pp. 91-93
Usual Hardware-Software Trend Comparison: Different counting rules
Try counting software as Lines of Code in Service (LOCS)
= (#platforms) *
(#object LOCS/platform) Usual Hardware-Software Trend Comparison Time Log N New transistors
in service/year New Source Lines of Code/year SW HW
Slide29: Lines of Code in Service: U.S. Dept. of Defense
Slide30: 1. DoD LOCS: % COTS, 2000 COTS often an economic necessity (<1%) M = Million, T = Trillion
2. Use of COTS Features: Microsoft Word and Power Point: 2. Use of COTS Features: Microsoft Word and Power Point Extra features cause extra work
Consider build vs. buy for small # features - K. Torii Lab, Japan: ISERN 2000 Workshop Individuals: 12-16% of features used
10-Person Group: 26-29% of features used
3. COTS Release Frequency: Survey Data: 3. COTS Release Frequency: Survey Data Adaptive maintenance often biggest CBS life cycle cost
Average of 3 releases before becoming unsupported - Ron Kohl/GSAW surveys: 1999-2002* * Ground System Architecture Workshops, Aerospace Corp.
4. CBS Effort Scaling As High As N2: 4. CBS Effort Scaling As High As N2 Strong COTS Coupling N + N(N-1)/2 =
N(N+1)/2 (here = 6) Effort ~ N (here = 3) Effort ~ Custom SW COTS Weak COTS Coupling COTS Custom SW COTS COTS COTS COTS
4. CBS Effort Scaling - II: 4. CBS Effort Scaling - II # COTS Relative COTS Adaptation Effort Reduce # COTS or Weaken COTS coupling
- COTS choices, wrappers, domain architectures,
open standards, COTS refresh synchronization
8
6
4
2 10 1 2 3 4 Strong COTS Coupling Weak COTS Coupling
Slide35: COTS Top-10 Empirical Hypotheses-II Less than half of CBS development effort comes from glue code
But glue code costs 3x more per instruction
Non-development CBS costs are significant
Worth addressing, but not overaddressing
COTS assessment and tailoring costs vary by COTS product class
Personnel factors are the leading CBS effort drivers
Different skill factors are needed for CBS and custom software
CBS project failure rates are higher than for custom software
But CBS benefit rates are higher also
6. COCOTS Effort Distribution: 20 Projects: 6. COCOTS Effort Distribution: 20 Projects - Mean % of Total COTS Effort by Activity ( +/- 1 SD ) 49.07% 50.99% 61.25% 20.27% 20.75% 21.76% 31.06% 11.31% -7.57% -7.48% 0.88% 2.35% -20.00% -10.00% 0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% assessment tailoring glue code system volatility % Person-months Glue code generally less than half of total
No standard CBS effort distribution profile
9. Personnel Factors Are Leading CBS Effort Drivers: Different Skill Factors Needed: 9. Personnel Factors Are Leading CBS Effort Drivers: Different Skill Factors Needed
Rethink recruiting and evaluation criteria Rqts./implementation assessment
Algorithms; data & control structures
Code reading and writing
Adaptation to rqts. changes
White-box/black-box testing Rqts./ COTS assessment
COTS mismatches; connector structures
COTS mismatches; assessment, tailoring, glue code development; coding avoidance
Adaptation to rqts., COTS changes
Black-box testing
10. CBS Projects Tend to Fail Hard Major Sources of CBS Project Failure: 10. CBS Projects Tend to Fail Hard Major Sources of CBS Project Failure
These are major topics for COTS risk assessment CBS skill mismatches
CBS inexperience
CBS optimism
Weak life cycle planning
CBS product mismatches
Hasty COTS assessment
Changing vendor priorities
New COTS market entries
Slide39: CBS Challenges Process specifics
Milestones; role of “requirements”
Multi-COTS refresh frequency and process
Life cycle management
Progress metrics; development/support roles
Cost-effective COTS assessment and test aids
COTS mismatch detection and redressal
Increasing CBS controllability
Technology watch; wrappers; vendor win-win
Better empirical data and organized experience
Software Engineering Trends: Software Engineering Trends
Integrating Software and Systems Engineering: Integrating Software and Systems Engineering The software “separation of concerns” legacy
Erosion of underlying modernist philosophy
Resulting project social structure
Responsibility for system definition
The CMMI software paradigm
The “Separation of Concerns” Legacy: The “Separation of Concerns” Legacy “The notion of ‘user’ cannot be precisely defined, and therefore has no place in CS or SE.”
Edsger Dijkstra, ICSE 4, 1979
“Analysis and allocation of the system requirements is not the responsibility of the SE group but is a prerequisite for their work.”
Mark Paulk at al., SEI Software CMM v.1.1, 1993
Cosmopolis: The Erosion of Modernist Philosophy: Cosmopolis: The Erosion of Modernist Philosophy Dominant since 17th century
Formal, reductionist
Apply laws of cosmos to human polis
Focus on written vs. oral; universal vs. particular; general vs. local; timeless vs. timely
one-size-fits-all solutions
Strong influence on focus of computer science
Weak in dealing with human behavior, rapid change
Resulting Project Social Structure: Resulting Project Social Structure
Responsibility for System Definition: Responsibility for System Definition Every success-critical stakeholder has knowledge of factors that will thwart a project’s success
Software developers, users, customers, …
It is irresponsible to underparticipate in system definition
Govt./TRW large system: 1 second response time
It is irresponsible to overparticipate in system definition
Scientific American: focus on part with software solution
The CMMI Software Paradigm: The CMMI Software Paradigm System and software engineering are integrated
Software has a seat at the center table
Requirements, architecture, and process are developed concurrently
Along with prototypes and key capabilities
Developments done by integrated teams
Collaborative vs. adversarial process
Based on shared vision, negotiated stakeholder concurrence
Systems Engineering Cost Model (COSYSMO) : Systems Engineering Cost Model (COSYSMO) Barry Boehm, Donald Reifer
and
Ricardo Valerdi
Development Approach: Development Approach Use USC seven step model building process
Keep things simple
Start with Inception phase first when only large-grain information tends to be available
Use EIA 632 to bound tasks that are part of the effort
Focus on software intensive subsystems first (see next chart for explanation), then extend to total systems
Develop the model in three steps
Step 1 – limit effort to software-intensive systems
Step 2 – tackle remainder of phases in life cycle
Step 3 – extend work to broad range of systems
Build on previous work
Slide49: The Form of the Model
COSYSMO
Size
Drivers Effort
Multipliers Effort Duration Calibration # Requirements
# Interfaces
# Scenarios
# Algorithms
+
Volatility Factor Application factors
8 factors
Team factors
8 factors
Schedule driver WBS guided
By EIA 632 COCOMO II-based model
Slide50: Step 2: Size the Effort Using Function Point Analogy Weightings of factors relative work use average requirement as basis To compute size, develop estimates for the drivers and then sum the columns
Slide51: Basic Effort Multipliers - I Detailed rating conventions will be developed for these multipliers Applications Factors (8)
Requirements understanding
Architecture understanding
Level of service requirements, criticality, difficulty
Legacy transition complexity
COTS assessment complexity
Platform difficulty
Required business process reengineering
Technology maturity
Slide52: Basic Effort Multipliers - II Detailed rating conventions will be developed for these multipliers Team Factors (8)
Number and diversity of stakeholder communities
Stakeholder team cohesion
Personnel capability
Personnel experience/continuity
Process maturity
Multi-site coordination
Formality of deliverables
Tool support
Slide53: Next Steps Data collection – gather actual effort and duration data from actual system engineering effort
Model calibration – calibrate the model first using expert opinion, then refine as actual data being collected
Model validation – validate that the model generates answers that reflect a mix of expert opinions and real-world data (move towards the actual data as it becomes available)
Model publication – publish the model periodically as new versions become available (at least bi-annually)
Model extension and refinement – extend the model to increase its scope towards the right; refine the model to increase its predictive accuracy
Software Engineering Trends: Software Engineering Trends
Value-Based Software Engineering (VBSE): Value-Based Software Engineering (VBSE) Essential to integration of software and systems engineering
Software increasingly determines system content
Software architecture determines system adaptability
7 key elements of VBSE
Implementing VBSE
CeBASE Method and method patterns
Experience factory, GQM, and MBASE elements
Means of achieving CMMI Level 5 benefits
7 Key Elements of VBSE: 7 Key Elements of VBSE Benefits Realization Analysis
Stakeholders’ Value Proposition Elicitation and Reconciliation
Business Case Analysis
Continuous Risk and Opportunity Management
Concurrent System and Software Engineering
Value-Based Monitoring and Control
Change as Opportunity
The Information Paradox (Thorp): The Information Paradox (Thorp) No correlation between companies’ IT investments and their market performance
Field of Dreams
Build the (field; software)
and the great (players; profits) will come
Need to integrate software and systems initiatives
DMR/BRA* Results Chain: DMR/BRA* Results Chain INITIATIVE OUTCOME OUTCOME Implement a new order
entry system ASSUMPTION Contribution Contribution Order to delivery time is
an important buying criterion Reduce time to process order Reduced order processing cycle
(intermediate outcome) Increased sales Reduce time to deliver product *DMR Consulting Group’s Benefits Realization Approach
Slide59: The Model-Clash Spider Web: Master Net
EasyWinWin OnLine Negotiation Steps: EasyWinWin OnLine Negotiation Steps
Slide62: Example of Business Case Analysis
ROI= (Benefits-Costs)/Costs Time Return on
Investment -1 1 2 3 Option B-Rapid Option B Option A
Architecture Choices: Architecture Choices Rigid Hyper-flexible Flexible
Architecture Flexibility Determination: Architecture Flexibility Determination
Value-Based Software Engineering (VBSE): Value-Based Software Engineering (VBSE) Essential to integration of software and systems engineering
Software increasingly determines system content
Software architecture determines system adaptability
7 key elements of VBSE
Implementing VBSE
CeBASE Method and method patterns
Experience factory, GQM, and MBASE elements
Means of achieving CMMI Level 5 benefits
Experience Factory Framework - III: Initiatives Planning context Progress/Plan/ Goal
Mismatches Experience Base Analyzed experience,
Updated models Achievables,
Opportunities Org. Improvement Goals
Goal-related questions, metrics
Org. Improvement Strategies
Goal achievement models Org. Improvement Initiative Planning & Control Initiative Plans
Initiative-related questions, metrics
Initiative Monitoring and Control
Experience-Base Analysis Org. Shared Vision & Improvement Strategy Experience Factory Framework - III Project Shared Vision and Strategy Planning Context Models and data Project experience Org. Goals Project Planning and Control Models and
data
VBSE Experience Factory Example: VBSE Experience Factory Example Shared vision: Increased market share, profit via rapid development
Improvement goal: Reduce system development time 50%
Improvement strategy: Reduce all task durations 50%
Pilot project: Rqts, design, code reduced 50%; test delayed
Analysis: Test preparation insufficient, not on critical-path
Experience base: OK to increase effort on non-critical-path activities, if it decreases time on critical-path activities
CeBASE Method Strategic Framework: CeBASE Method Strategic Framework
Org. Value Propositions (VP’s)
-Stakeholder values
Current situation w.r.t. VP’s
Improvement Goals, Priorities
Global Scope, Results Chain
Value/business case models
Org-Portfolio Shared Vision
Strategy elements
Evaluation criteria/questions
Improvement plans
-Progress metrics
-Experience base Org. Strategic Plans Organization/
Portfolio:
Experience
Factory,
GQM
Monitor environment
-Update models
Implement plans
Evaluate progress
-w.r.t. goals, models
Determine, apply
corrective actions
Update experience base Org. Monitoring & Control Monitoring
& Control
Context
Project Value Propositions
-Stakeholder values
Current situation w.r.t. VP’s
Improvement Goals, Priorities
Project Scope, Results Chain
Value/business case models Project Shared Vision Project:
MBASE Planning
context Plan/Goal mismatches Project Plans Planning
Context Initiatives Progress/Plan/Goal mismatches
-shortfalls, opportunities,
risks Project
vision,
goals Shortfalls,
opportunities,
risks Scoping
context Shortfalls,
opportunities,
risks Planning
Context
Monitor environment
-Update models
Implement plans
Evaluate progress
-w.r.t. goals, models,
plans
Determine, apply
corrective actions
Update experience base Proj. Monitoring & Control Monitoring
& Control
context Progress/Plan/goal mismatches
-Shortfalls, opportunities, risks Plan/goal mismatches Monitoring
& Control
context Project
experience,
progress w.r.t.
plans, goals LCO: Life Cycle Objectives
LCA: Life Cycle Architecture
IOC: Initial Operational Capability
GMQM: Goal-Model-Question-Metric Paradigm
MBASE: Model-Based (System) Architecting and Software Engineering -Applies to organization’s and projects’ people, processes, and products
LCO/LCA Package
-Ops concept, prototypes,
rqts, architecture,
LCplan, rationale
IOC/Transition/Support Package
-Design, increment plans,
quality plans, T/S plans
Evaluation criteria/questions
Progress metrics
CeBASE Method Coverage of CMMI - I: CeBASE Method Coverage of CMMI - I Process Management
Organizational Process Focus: 100+
Organizational Process Definition: 100+
Organizational Training: 100-
Organizational Process Performance: 100-
Organizational Innovation and Deployment: 100+
Project Management
Project Planning: 100
Project Monitoring and Control: 100+
Supplier Agreement Management: 50-
Integrated Project Management: 100-
Risk Management: 100
Integrated Teaming: 100
Quantitative Project Management: 70-
CeBASE Method Coverage of CMMI - II: CeBASE Method Coverage of CMMI - II Engineering
Requirements Management: 100
Requirements Development: 100
Technical Solution: 60+
Product Integration: 70+
Verification: 70-
Validation: 80+
Support
Configuration Management: 70-
Process and Product Quality Assurance: 70-
Measurement and Analysis: 100-
Decision Analysis and Resolution: 100-
Organizational Environment for Integration: 80-
Causal Analysis and Resolution: 100
CeBASE Method Simplified via Method Patterns: CeBASE Method Simplified via Method Patterns Schedule as Independent Variable (SAIV)
Also applies for cost, cost/schedule/quality
Opportunity Trees
Cost, schedule, defect reduction
Agile COCOMO II
Analogy-based estimate adjuster
COTS integration method patterns
Process model decision table
The SAIV Process Model: The SAIV Process Model 1. Shared vision and expectations management
2. Feature prioritization
3. Schedule range estimation
4. Architecture and core capabilities determination
5. Incremental development
6. Change and progress monitoring and control
Shared Vision, Expectations Management, and Feature Prioritization: Shared Vision, Expectations Management, and Feature Prioritization Use stakeholder win-win approach
Developer win condition: Don’t overrun fixed 24-week schedule
Clients’ win conditions: 56 weeks’ worth of features
Win-Win negotiation
Which features are most critical?
COCOMO II: How many features can be built within a 24-week schedule?
COCOMO II Estimate Ranges: COCOMO II Estimate Ranges
Core Capability Incremental Development, and Coping with Rapid Change: Core Capability Incremental Development, and Coping with Rapid Change Core capability not just top-priority features
Useful end-to-end capability
Architected for ease of adding, dropping marginal features
Worst case: Deliver core capability in 24 weeks, with some extra effort
Most likely case: Finish core capability in 16-20 weeks
Add next-priority features
Cope with change by monitoring progress
Renegotiate plans as appropriate
SAIV Experience I: USC Digital Library Projects: SAIV Experience I: USC Digital Library Projects Life Cycle Architecture package in fixed 12 weeks
Compatible operational concept, prototypes, requirements, architecture, plans, feasibility rationale
Initial Operational Capability in 12 weeks
Including 2-week cold-turkey transition
Successful on 24 of 26 projects
Failure 1: too-ambitious core capability
Cover 3 image repositories at once
Failure 2: team disbanded
Graduation, summer job pressures
Slide77: RAD Opportunity Tree Business process reengineering Eliminating Tasks Reducing Time Per Task Reducing Risks of Single-Point Failures Reducing Backtracking Activity Network Streamlining Increasing Effective Workweek Better People and Incentives Transition to Learning Organization Reusing assets Applications generation Schedule as independent variable (SAIV) Tools and automation Work streamlining (80-20) Increasing parallelism Reducing failures Reducing their effects Early error elimination Process anchor points Improving process maturity Collaboration technology Minimizing task dependencies Avoiding high fan-in, fan-out Reducing task variance Removing tasks from critical path 24x7 development Nightly builds, testing Weekend warriors
Software Engineering Trends: Software Engineering Trends
Slide79: Understanding, dealing with sources of software value
And associated stakeholders, applications domains
Software/systems architecting and engineering
Creating and/or integrating software components
Using risk to balance disciplined and agile processes
Ability to continuously learn and adapt Critical Success Factors for Software Careers
Slide80: Understanding, dealing with sources of software value
And associated stakeholders, applications domains
CS 510: Software Management and Economics
Software/systems architecting and engineering
Creating and/or integrating software components
Using risk to balance disciplined and agile processes
CS 577ab: Software Engineering Principles and Practice
CS 578: Software Architecture
Ability to continuously learn and adapt
CS 592: Emerging Best Practices in Software Engineering - USC Software Engineering Certificate Courses Critical Success Factors for Software Careers
USC SWE Certificate Program and MS Programs Provide Key Software Talent Strategy Enablers: USC SWE Certificate Program and MS Programs Provide Key Software Talent Strategy Enablers Infusion of latest SWE knowledge and trends
Tailorable framework of best practices
Continuing education for existing staff - Including education on doing their own lifelong learning
Package of career-enhancing perks for new recruits - Career reward for earning Certificate - Option to continue for MS degree - Many CS BA grads want both income and advanced degree
Available via USC Distance Education Network
Conclusions : Conclusions World of future: Complex adaptive systems
Distribution; mobility; rapid change
Need adaptive vs. optimized processes
Don’t be a process dinosaur
Or a change-resistant change agent
Marketplace trends favor value/risk-based processes
Software a/the major source of product value
Software the primary enabler of system adaptability
Individuals are organizations need pro-active software talent strategies
Consider USC SW Engr. Certificate and MS programs
Slide83: References D. Ahern, A.Clouse, & R. Turner, CMMI Distilled, Addison Wesley, 2001.
C. Baldwin & K. Clark, Design Rules: The Power of Modularity, MIT Press, 1999.
B. Boehm, D. Port, A. Jain, & V. Basili, “Achieving CMMI Level 5 with MBASE and the CeBASE Method,” Cross Talk, May 2002.
B. Boehm & K. Sullivan, “Software Economics: A Roadmap,” The Future of Software Economics, A. Finkelstein (ed.), ACM Press, 2000.
R. Kaplan & D. Norton, The Balanced Scorecard: Translating Strategy into Action, Harvard Business School Press, 1996.
D. Reifer, Making the Software Business Case, Addison Wesley, 2002.
K. Sullivan, Y. Cai, B. Hallen, and W. Griswold, “The Structure and Value of Modularity in Software Design,” Proceedings, ESEC/FSE, 2001, ACM Press, pp. 99-108.
J. Thorp and DMR, The Information Paradox, McGraw Hill, 1998. Software Engineering Certificate website: sunset.usc.edu/SWE-Cert
CeBASE web site : www.cebase.org
CMMI web site : www.sei.cmu.edu/cmmi
MBASE web site : sunset.usc.edu/research/MBASE