Slide 1: 

Wrightington, Wigan & Leigh NHS Trust Construction Sequence Stage 3 - 2nd Fix SteelWork Stage 4 – Unistrut Services Support Frame Stage 5 – Services Installation Stage 7 – Mezzanine Floor Installation Stage 6 – 1st Side Partition Installation Stage 8 – Partition Service Drops Stage 9 – 2nd Side Partition Installation Stage 10 – Floor Finishes Stage 11 – Installation Of Client Equipment Stage 12 – Door & Vision Panel/Window Installation Stage 14 – Service Drops To Client Equipment Stage 13 – 2nd Fix HVAC Terminals & Lighting Stage 15 – Final Fix Electrical Equipment Stage 16 – Commissioning & Validation Stage 2 – Floor Screed SSD Facility Available For Construction Commencement Stage 1 – Drainage Channels & Civil Works