Maintenance and BuildingConceptual Approach : Maintenance and Building Conceptual Approach L. Waganer and R. Peipert
The Boeing Company
4 October 2006
PPPL Project Meeting
Maintenance Design Approach: Maintenance Design Approach Port maintenance adopted, replacing large blanket and divertor modules
Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.
Blanket and divertor modules removable inside core
ECH launcher designed as a removable assembly
All power core maintenance fully robotic and automated based on prototypes and production plants
Work simultaneously on all three field periods
Employ maintenance machines inside fixed port transfer chambers just outside bio-shield
Pass all used and new modules via airlocks to mobile transporters
If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.
Compare similar 1950’s and 2000’s technologies and Project into the Future!: Compare similar 1950’s and 2000’s technologies and Project into the Future! Automobile Assembly
Surgery (knee, hernia, heart, lung )
Vision Correction (glasses vs. laser)
Electronics (transistor vs. LSIC)
Data Storage (tape drive » floppy drive » hard drive » solid state) (20 yr time span) Deburring movie Tool Changer movie How To Forecast Maintenance Technologies 40-50 Years in Future? Consider physical laws as limiting values
Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports: Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports Simultaneous maintenance in 3 FP
Fixed Transfer Chambers control contamination and enhance times
Mobile Transporters transfer used and new components to/from Hot Cell
Main Port is used for removing blanket and divertor modules
ECH launcher/waveguide removed as an assembly
ECH port can then be used as Auxiliary maintenance port
Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support
Example of Pallet Transfer Technology for ECH Module Assembly: Example of Pallet Transfer Technology for ECH Module Assembly We may want to adapt a conveyor approach similar to the efficient pallet handling transfer system used in freighter aircraft, C5, C17, C141, et. al.
Slide6: Removable ECH Assembly at 35º Port
ECH Waveguide, 0.54 m H x 0.24 m W
Opening in VV and Coil Structure, 1.54m H x 1.24 m W
Opening through Bioshield, 1.6 m H x 1.6 m W Note: Removable ECH Module includes
Waveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel Permanent
Transfer Chamber
Slide7: Extraction of ECH Assembly Into Transfer Chamber Maintenance machine removes waveguide segment and coolant coupling
Complete assembly removed into Transfer Chamber by pallet system
Slide8: ECH Module Moved Into Mobile Transporter
for Transit to Hot Cell for Refurbishment
ECH/Aux Port Maintenance Actions: ECH/Aux Port Maintenance Actions Removes blanket shielding blocks, shielding rings, and cuts coolant tubes while main port arm supports and removes blankets
View of Main Port (0º), Operational: View of Main Port (0º), Operational
Initial Position of Extractor Machine: Initial Position of Extractor Machine This is the position of Extractor after plasma shutdown and cool-down
First Action Is To Remove Bioshield Door: First Action Is To Remove Bioshield Door After the door is positioned inside Transfer Chamber, bridging structure is positioned
Vacuum vessel door and port shielding is removed and set aside inside Transfer Chamber
Removal of Port Manifold/Structure: Removal of Port Manifold/Structure The manifold/hot structure connections are disconnected and the structure is removed and set aside
Removal of Port Blanket and Shield: Removal of Port Blanket and Shield This port blanket and shield module is the largest component to be removed
It is also the only module that has an integral shield
It is sized to clear port opening and provide maximum access to interior of power core
Design Approach to Extract Inner Coolant Tube and Shielding to Access Welded Joint : Design Approach to Extract Inner Coolant Tube and Shielding to Access Welded Joint If welded joints are to be used to secure outer divertor coolant tubes, joint must be shielded
Entire inner tube and shielding assembly is removed allowing access to outer tube weld region
Access is from outside of coil structure near center of machine
Removal of Divertor Tubes and Shielding: Removal of Divertor Tubes and Shielding The inner tubes and shielding for the Divertor plates are removed by floor and ceiling mounted manipulators (24 places at ± 12.5°)
This is done simultaneously with ECH assembly removal and main port opening procedures
Preparation for Divertor Plate Removal: Preparation for Divertor Plate Removal This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support
The Diverter plates span two blanket modules but they fit through the main port opening
Divertor Plate Removal: Divertor Plate Removal This view shows the removal of the Divertor plates
After removal, they are moved to the Hot Cell via the Mobile Transporter
During this step, the inner manipulator can be removing other coolant tube assemblies
Removal of Blanket Modules: Removal of Blanket Modules This is a typical procedure for removal of the blanket modules
The Blanket modules are attached to the Hot Shield with four fasteners deep within the blanket close to the Hot Shield
Tools disengage the fasteners while gripping the walls of the access holes, thus providing holding force for fastener removal and blanket handling
Removal of Blanket Module (Cont’d): Removal of Blanket Module (Cont’d) Blanket module is being removed from Power Core and placed in Mobile Transporter
As soon as this module is moved from its position on the Hot Shield, the Auxiliary Manipulators can begin to remove the shield blocks and shield rings for access to and severing the Blanket coolant tubes
Maintenance and Availability Analysis: Maintenance and Availability Analysis
Alternative to Cutting and WeldingBlanket Coolant Tubes: Alternative to Cutting and Welding Blanket Coolant Tubes Current Technology
Embed shielding blocks and rings to protect weld region
Time-consuming procedure that generates contamination Proposed Future Technology
Remotely operated coolant clamp, Marmon type?
Clamp and actuating mechanism can be replaced during refurbishment period
Eliminates need for auxiliary port and equipment
Reduces core maintenance time by factor of 4
Maintenance and Availability Analysis: Maintenance and Availability Analysis
Maintenance Slides for Engineering Summary: Maintenance Slides for Engineering Summary
Maintenance Design Approach: Maintenance Design Approach Port maintenance adopted, replacing large blanket and divertor modules
Replace all first wall/blanket and diverter modules ECH launchers every 3.0 FPY. Remainder is life-of-plant.
Blanket and divertor modules removable inside core
ECH launcher designed as a removable assembly
All power core maintenance fully robotic and automated based on prototypes and production plants
Work simultaneously on all three field periods
Employ maintenance machines inside fixed port transfer chambers just outside bio-shield
Pass all used and new modules via airlocks to mobile transporters
If conventional tube welding is used, auxiliary maintenance machines ports are needed. Remote disconnects would cut maintenance time by a factor of 4.
Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports: Mid-Plane View Shows Maintenance At Main and ECH/Aux Maintenance Ports Simultaneous maintenance in 3 FP
Fixed Transfer Chambers control contamination and enhance times
Mobile Transporters transfer used and new components to/from Hot Cell
Main Port is used for removing blanket and divertor modules
ECH launcher/waveguide removed as an assembly
ECH port can then be used as Auxiliary maintenance port
Manipulators inside Bioshield at center of power core remove divertor inner tubes and shielding and cut outer divertor tube/support
Slide27: Removable ECH Assembly/ Auxiliary Maintenance Port
Removable ECH Module includes Waveguide, All Shielding, Bioshield, Mirror, and Exo-Bioshield Vacuum Vessel
Entire module assembly can be withdrawn into Transfer Chamber Permanent
Transfer Chamber Aux Manipulator removes blanket shielding blocks, shielding rings, and cuts coolant tubes while main port arm supports and removes blankets ECH Module Moved Into Mobile Transporter for Transit to Hot Cell for Refurbishment
Preparation for Divertor Plate Removal: Preparation for Divertor Plate Removal This depicts the main port Extractor holding the Divertor Plates (24 pl) while the cutting bore tool on the central manipulator severs the outer coolant tube, which is the Divertor structural support
The Diverter plates span two blanket modules but they fit through the main port opening
Maintenance and Availability Analysis: Maintenance and Availability Analysis