Structures Over 40 Years Old - Part A

Views:
 
Category: Education
     
 

Presentation Description

This presentation was prepared in February 2013 by the Municipal Engineers Association to assist with understanding and applying the Municipal Class Environmental Assessment. Be sure to download the check list from www.municipalclassea.ca and complete this check list while viewing Parts A, B, C and D of the Structures over 40 years module Click on the "Download" button above the presentation and to the right, to have a PowerPoint version of this presentation which includes written text of the dialog

Comments

Presentation Transcript

Municipal Heritage Bridges and Application of the Municipal Class Environmental Assessment:

Municipal Heritage Bridges and Application of the Municipal Class Environmental Assessment

Objectives :

Objectives Select appropriate Schedule; Assess cultural heritage value; Assess archaeological resources;

MCEA Project Schedules:

MCEA Project Schedules Activities 24 – 31 Schedule A, A+, B or C

MCEA Project Schedules:

MCEA Project Schedules 30. Reconstruction or alteration of a structure of the grading adjacent to it when the structure is over 40 years old (where the proposed work will alter the basic structural system), which after appropriate evaluation is found to have cultural heritage value. 31. Reconstruction or alteration of a structure or the grading adjacent to it when the structure is over 40 years old which after appropriate evaluation is found not to have cultural heritage value. Determination of cultural heritage value will be in accordance with a screening checklist developed with the Ministry of Tourism and Culture (MTC) and posted on the MEA website.

Select Project Type from MCEA:

Select Project Type from MCEA Print checklist to record determination of project schedule

PowerPoint Presentation:

Will the proposed project involve or result in construction of new water crossings? This includes ferry docks. Yes – Schedule B or C No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in construction of a new grade separation? Yes – Select B or C No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in construction of new underpasses or overpasses for pedestrian, recreational or agricultural use? Yes – Select B or C No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in construction of new interchanges between any two roadways, including a grade separation and ramps to connect the two roadways? Yes – Schedule B or C No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in reconstruction of a water crossing where the structure is less than 40 years old and the reconstructed facility will be for the same purpose, use, capacity and at the same location? (Capacity refers to either hydraulic or road capacity.) This includes ferry docks. Yes – Schedule A+ No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in reconstruction of a water crossing, where the reconstructed facility will not be for the same purpose, use, capacity or at the same location? (Capacity refers to either hydraulic or road capacity). This includes ferry docks. Yes – Schedule B or C No - Next PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Will the proposed project involve or result in reconstruction or alteration of a structure or the grading adjacent to it when the structure is over 40 years old where the proposed work will alter the basic structural system, overall configuration or appearance of the structure? Yes – Part B Cultural Heritage Assessment No – Assess Archaeological Resources PART A MCEA PROJECT TYPE SELECTION

PowerPoint Presentation:

Repairs that do NOT alter are Schedule A PART A MCEA PROJECT TYPE SELECTION