Hydropower Projects in Nepal : Hydropower Projects in Nepal D Bhattarai
Deputy Director General
Department of
Electricity Development
Ministry of Water Resources
Slide2 : Nepal in Region
Country Profile : Country Profile Area : 147,181 km2
Population : 2,32,14,681 (2001)
GDP : 5.9 B US$ (2003)
Average annual flow : 225 Billion CM
Theoretical generation capacity : 83,000 MW
Economically feasible capacity : 44,000 MW
Present installed capacity (hydro) : 590 MW
Slide4 : Major River Basins and
Hydropower Projects in Nepal
Slide5 : Private Sector Projects
SN Project (MW) Promoter Status
1. Khimti-1 (60) HPL Completed
2. Upper Bhote Koshi (36) BKPC Completed
3. Indrawati-3 (7.5) NHPC Completed
4. Chilime (20) CPC Completed
Piluwa (3) AVHDC Completed
Syange (0.18) LEDCO Completed
Sunkoshi (2.6) SHPL Completed
Chaku (1.5) APN Completed
Hydropower Projects : Nepal : Hydropower Projects : Nepal Upper (335),
Arun III (402) &
Lower Arun (308) Upper
Tamakoshi (309) Upper
Karnali (300) Karnali
Chisapani(10800) Kali
Gandaki 2(660) Budhi
Gandaki (600) Dudh
Koshi (300))
Slide7 : Project Features : Lower Arun
Eastern Development
Sankhuwasabha
Run-of-River (Daily Pondage)
308 MW ( 4x77 MW )
212.2 m
171.5 m3/Sec
10.5 m
Underground
15.2 km / 8.4m
2275.9 GWh
1436.5 GWh
25 km from Arun-3 damsite
100 km (220 kV)
US$ 481.4 million (1990)
Location
Region :
District :
Type :
Installed Capacity :
Net Rated Head :
Design discharge :
Weir Height :
Power House Type :
Power Tunnel Length & Dia :
Average Annual Energy :
Firm Energy :
Access Road Length :
Transmission Length :
Project Cost : Status: Pre-Feasibility Study, 1990
Slide8 : Project Features : Arun 3
Eastern Development
Sankhuwasabha
Pondage Run-of-River
402 MW ( 6 x 67 MW )
303.8 m
320 m3/sec
68 m
Underground
Underground
11.5 km/7.5 m
2891 GWh
1558 GWh
116.8 km
432.2 km(220 kV double crt.)
US$ 859.09 million (1995)
Location
Region :
District :
Type :
Installed Capacity :
Gross Head :
Design Discharge :
Dam Height :
Power House Type :
Desander Type :
Tunnel Length & Dia. :
Average Annual Energy :
Firm Energy :
Access Road Length :
Transmission Length :
Project Cost :
Status: Detailed Design Study
Slide9 : Project Features : Upper Arun Location
Region :
District :
Type :
Installed Capacity :
Net rated Head :
Dam Height :
Design Discharge :
Power House Type :
Tunnel Length & Size :
Average Annual Energy :
Access Road Length :
Transmission Length :
Project Cost :
Eastern Development
Sankhuwasabha
Run-of-River (Daily Pondage)
335 MW ( 4 x 83.75 )
492 m
37 m
78 m3/Sec
Underground
7.84 km & 5.5 m
2050 GWh
45 km from Arun-3 damsite
200 km (220 kv)
US$ 508.8 million (1991)
Status: Feasibility Study, 1991
Slide10 : Upper Arun
Arun 3
Lower Arun
Slide11 : Project Features : Dudh Koshi Location
Region :
District :
Type :
Installed Capacity :
Net Rated Head :
Design Discharge :
Dam Height :
Live Storage :
Power House Type :
Average Annual Energy :
On Peak Firm Energy :
Off Peak Firm Energy :
Access Road Length :
Transmission Length :
Project Cost :
Eastern Development
Okhaldunga, Khotang
Storage
300 MW (5x60 MW)
249.3 m
136 m3/s
180 m
442.1 million cubic metre
Underground
1806 GWh
552 GWh
920 GWh
43.2 km
93 km (220kv Duble crt.)
135 km (220 kv Single crt.)
US$ 690.1 million (1998)
`
Status: Feasibility Study, 1998
Slide12 : Location
Dudhkoshi
Hydropower Project (300 MW)
Slide13 : Project Features : Upper Tamakoshi
Eastern Region
Dolakha
PROR
309 MW
820 m
44 m3/Sec
177 m
Surface
7170 m
3470 GWh
61 km
47 km (220 kV)
US$ 340 million (2005)
Location
Region :
District :
Type :
Installed Capacity :
Net Rated Head :
Design Discharge :
Dam Height :
Power House Type :
Tunnel Length :
Average Annual Energy :
Access Road Length :
Transmission Length :
Project Cost :
Status: Feasibility Study, 2005
Slide14 : Upper Tamakoshi
Hydropower Project (309 MW)
Slide15 : Project Features : Budhi Gandaki
Central/Western Development
Dhadhing/Gorkha
Storage
600 MW ( 4 x150 MW )
185 m
430 m3/s
225 m
2755 million cubic meter
Rockfill with inclined core
Underground
276 m /12m
2495 GWh
2.5 km
65 km (220 kv)
US$ 774 million (1983)
Location
Region :
District :
Type :
Installed Capacity :
Net Head :
Design Discharge :
Dam Height :
Live storage :
Dam Type :
Power House Type :
Tunnel Length & Dia :
Average Annual Energy :
Access Road Length :
Transmission Length :
Project Cost :
Status: Pre-Feasibility Study, 1984
Slide16 : Location
Budhi Gandaki
Hydropower Project
Slide17 : Project Features : Kali Gandaki 2
Western Region
Nawalparsi and Tanahu
Storage
660 MW (6 x 110 MW)
128.3 m
585 m3/Sec
177 m
Surface
322 m /6 m
3470 GWh
20 km
40 km (220 kv)
US$ 772 million (1985)
Location
Region :
District :
Type :
Installed Capacity :
Net Rated Head :
Design Discharge :
Dam Height :
Power House Type :
Tunnel Length & Dia :
Average Annual Energy :
Access Road Length :
Transmission Length :
Project Cost :
Status: Pre-Feasibility Study, 1985
Slide19 : Project Features : Upper Karnali Location :
Type :
Installed Capacity :
Gross Head :
Design Discharge :
Weir Height
Power House Type :
Desander Type :
Tunnel Length & Dia. :
Average Annual Energy :
Firm Energy :
Access Road Length :
Transmission Length :
Project Cost : Mid/Far Western Region
Run-of-River (Pondage)
300 MW
141 m
236 m3/s
27 m
Underground
Surface
2.2 km & 11.35 m
1915 GWh
1159 GWh
22 km
215 km (220 kv)
US$ 454.3 million (1998)
Status: Feasibility Study 1998
Slide20 : Location
Upper Karnali Project
Slide21 : Project Features : Karnali (Chisapani)
Mid-Western Development
Bardiya/Achham
Storage
10800 MW ( 18 x600 MW )
1390 m3/s
270 m
16.2 billion cubic meter
Rockfill with inclined core
Underground
276 m /12m
20842 GWh
2.5 km
300 km (765 kV to India)
US$ 4890 million (1989)
Location
Region :
District :
Type :
Installed Capacity :
Average Discharge :
Dam Height :
Live storage :
Dam Type :
Power House Type :
Tunnel Length & Dia :
Average Annual Energy :
Access Road Length :
Transmission Length :
Project Cost :
Status: Pre-Feasibility Study, 1984
Slide22 : Karnali (Chisapani) Multipurpose Project
Slide23 : Thank You