Overview of Braidwood Reactor Experiment : Overview of Braidwood Reactor Experiment Introduction to Braidwood site
General strategy and layout of experiment
Underground construction estimate
Plans E. Blucher, Chicago Niigata Workshop
Slide2 : Midwest Collaboration ANL: Maury Goodman, David Reyna
Chicago: Erin Abouzaid, Kelby Anderson, Ed Blucher, Jim Pilcher, Matt Worcester
Columbia: Janet Conrad, Jon Link, Mike Shaevitz
FNAL: Larry Bartoszek, Dave Finley, Hans Jostlein, Chris Laughton, Ray Stefanski
Kansas: Tim Bolton, Noel Stanton
Oxford: Steve Biller, Nick Jelley
Pittsburgh: Donna Naples, Vittorio Paolone
Texas: Josh Klein
Slide3 : We considered several sites in Illinois (Braidwood, Byron, Lasalle) and Kansas (Wolf Creek).
We have focused on the Braidwood site managed by Exelon Nuclear.
Braidwood:
23.6 GW reactors –
7.17 GW (thermal) maximum power
Efficient operation: 90% capacity
factor over last several years.
Slide4 : Braidwood site
Slide5 : Braidwood site Features of Braidwood site:
23.6 GW reactors – 7.17 GW maximum power
Flat: flexibility, equal overburden at near and far sites, surface
transportation of detectors
Favorable geology (dolomitic limestone): good for excavation,
low radioactivity (order of magnitude lower U, Th than granite)
Slide6 : II. sin2W: If possible, maintain design that will allow measurement
of sin2W using antineutrino-electron elastic scattering in near
detector. Ideally, near detector should be close to reactor, deep,
and have the same overburden as far detector (to allow
measurement of environmental backgrounds using far detector).
See talk by M. Shaevitz this afternoon. Physics Goals of Experiment If sin22 is relatively large (e.g. observable by Double Chooz),
a precision measurement will be needed to combine with
accelerator experiments. I. sin22~0.01: If sin22 < 0.01, it will be difficult for long-
baseline “superbeam” experiments to investigate mass
hierarchy and CP violation. Reactor experiment with sensitivity
of 0.01 will indicate scale of future experiments needed to make
progress.
Slide7 : Detector Concept ~200 m ~1600 m General Strategy of Experiment 1 near detector and 2 far detectors (at oscillation maximum)
6.5 m diameter spherical detectors with 3 zones (Gd-loaded scint.)
25-50 ton fid. mass per detector, depending on required buffer regions
Movable detectors with surface transport for cross-calibration; vertical
shaft access to detector halls
Full detector construction above ground
Near and far detectors at same depth of 450 mwe (contingent
on bore holes)
Near detector at ~200 m security perimeter (L~270 m); far detectors
at ~1800 m
Slide8 : 3-zone Gd-based Detector I II III I. Gd-loaded liquid scintillator
II. catcher: liquid scintillator (no Gd)
III. Non-scintillating buffer R=1.9 m, m=25 tons
R=2.4 m
R=3.25 m 6.5 m R=2.4 m, m=50 tons
R=2.7 m
R=3.25 m Total detector mass ~150 tons PMTs Two examples:
Slide9 : Detector Optimization We’ve developed a hit-level Monte Carlo for initial design
studies. In parallel, we’re developing a Geant-4 based detector
model. Currently studying detector
optimization:
required buffer thicknesses
active and passive shielding
Slide10 : Relative Acceptance Strategy Measure relative acceptances by cross-calibrating detectors
at near detector location: surface movement of detectors Establish relative acceptances as well as possible without detector movement – careful detector construction, radioactive sources, reactor interactions, cosmics, etc. For example: n+H n+Gd
Slide11 : E.g., 750-ton capacity crawler crane performing test lift of 750 tons Relatively flat terrain allows
“inexpensive” movement
of detectors on surface. Many crane options with adequate capacity Surface movement either with
multi-axle “truck” on gravel
road or with surface rail system
(depends on acceptable stresses)
Slide12 : Example of transporter moving 550 ton drum from ship to crane hook
Slide13 : Conceptual Mechanical Design Design issues:
Support for concentric acrylic vessels
Integration of source calibration system with vessel support
Integration of detector design with surface movement (i.e.,
what is maximum safe instantaneous acceleration?)
Engineering of active and passive veto system
Underground Construction Estimate : Underground Construction Estimate
A detailed estimate of cost and schedule for underground construction
at the Braidwood site was recently performed by Hilton and
Associates, Inc. (tunnel cost estimating consultants).
Complete estimate of costs associated with underground facility;
including all civil construction, underground outfitting (pumps,
elevators, ventilation, etc.); even includes cost associated with
decommissioning shafts at end of experiment.
Does not include permanent surface buildings or detectors.
Components of cost separated in enough detail to allow scaling
of costs with changes in design.
Slide15 : Braidwood Site Reactors Controlled perimeter
Slide16 : Layout for underground construction estimate Far shaft Near shaft Near detect. hall Reactors Braidwood
Layout for Underground Construction Estimate : Layout for Underground Construction Estimate
Near & Far Shaft Layouts : Near & Far Shaft Layouts Not to Scale Tunnel cross section
Slide19 : Two Styles of Detector Halls Near hall: Far hall: 12 14 15 m 12 14 32 m 12 m 12 m 2 m Detector hall cross section
Slide20 : Two Styles of Detector Halls Near hall: Far hall: 12 14 15 m 12 14 32 m 12 m Detector hall will accommodate
active and passive shielding tracking passive
shielding
Slide21 : Layout used for underground construction estimate:
300 mwe, two shafts, different detector hall designs, 300m tunnel
Cost: $35 million; Time: 39 months with sequential construction.
Revised layout:
Increase depth to 450 mwe (160 m rock + 20 m soil) contingent
on bore hole results
Site near detector shaft to shorten or eliminate tunnel stub
Use near hall design at both near and far sites
Cost: $25-35 million
Time: ~36 months with sequential construction of near and far
sites; < 2 years with simultaneous construction of sites.
Slide22 : Revised Layout Far shaft Reactors Braidwood Site near shaft
to shorten or
eliminate tunnel
Conclusions : Conclusions Settle surface layout (location of shafts, infrastructure for detector movement) in consultation with Exelon.
Drill bore holes to full depth at both shaft positions: provides info about geology, radioactivity, density; will reduce contingency required for construction.
Optimize detector design for acceptance uncertainty and background rejection (buffer regions, calibration system, active and passive shielding, etc.) Braidwood site appears very attractive
High power reactor with cooperative management
Can use vertical shafts to reach necessary depth
Surface movement of detectors seems technically feasible. Short-term Plans: