protonplan PMG 20060525 prebys

Uploaded from authorPOINTLite
Views:
 
Category: Entertainment
     
 

Presentation Description

No description available.

Comments

Presentation Transcript

Proton Plan Status April Report: 

Proton Plan Status April Report Eric Prebys

Agenda: 

Agenda Shutdown/Startup – Prebys Technical Status - Prebys Cost/Schedule Report – Sims Corrector Project - Drennan

Slide3: 

Shutdown and Startup

Review of Major Shutdown Work: 

Review of Major Shutdown Work Re-routed 400 MeV Line Injection Girder

MI-8 Dump Line: 

MI-8 Dump Line Relocated Septum Dump New Dump Line

MI-8 Collimator: 

MI-8 Collimator Note marble cladding

Main injector large aperture quads (7): 

Main injector large aperture quads (7)

Other Proton Plan Shutdown Projects: 

Other Proton Plan Shutdown Projects Booster 13.8V transformer and switch gear upgrade: Recommended for reliable 9Hz operation New system will go to 15 Hz Water routing for eventual corrector upgrade RF cavity drift tube cooling complete MI-10 kicker upgraded with new load and cooling to handle high rep. rates needed for NuMI slip stacking. Lots of useful low level RF measurements in the Linac.

Major non-Proton Plan Work: 

Major non-Proton Plan Work Booster Sump rerouting RF Significant maintenance work, including recovery from “water incident” A/B switch installed so cavity 19th cavity can be used as a proper spare. Time with at least 18 working cavities should go from ~80% to >95%. 400 MeV Line power supply upgrade: Replace unreliable Power 10 supplies with more robust Lambda supplies (good idea) Replace custom CAMAC controller with Allen-Bradley PLC (jury still out)

Acknowledgements: 

Acknowledgements This shutdown ran like clockwork thanks to the work of countless people in the Proton Source, Main Injector, Project Support, Mechanical Support, and EE Support Departments, as well as Technical Division and the AMG. We’d also like to thank Safety for working with us to insure that we had everything in order for an efficient sign-off. As usual, Operations has played a big role in our smooth turn on.

Booster Startup Summary: 

Booster Startup Summary The good news: It appears we didn’t do anything stupid Timeline (note, we worked around daytime tunnel work): Friday 5/12 19:00 - First attempt at 400 MeV beam 21:00 - Beam to injection toroid Saturday 5/13 02:00 – Beam through ORBUMP into Booster 05:00 – Beam around Booster Sunday 5/14 02:00 – DC beam for up to 33 ms Tuesday 5/16 ~19:00 – Accelerate beam and extract. Get beam to new septum on first extraction attempt. Fail to hit new dump target in several hours Wednesday 5/17 15:00 – After correcting for a miscalculation in the required septum current, establish beam to new dump! Currently Tuning and optimizing Demonstrated 3E12 proton batches with reasonable efficiency

Understanding ORBUMP: 

Understanding ORBUMP Saturation of the central magnet: Causes a net integrated dipole moment (like a one bump). Measurements were inconsistent, but it’s on the order of 1%, which could cause a 4 mm closed orbit distortion as ORBUMP slews down. Doing measurements with various current shunts on end magnets to calculate the optimum shunt to cancel effect. End to end mismatch: Causes a lateral displacement (like a single dogleg) Measured to be .4% with an imbalance toroid. This should cause a maximum of 0.6 mm closed orbit distortion. Can cancel it by modifying stripline to increase inductance.

MI Startup Summary: 

MI Startup Summary Monday 5/22 1630 – Circulating Beam in MI on first shot! Tuesday 5/23 1400 – Beam to 120 GeV flat top Discovered problem with regulation of new quads, since fixed. Wednesday 5/24 2200 – Beam to 150 GeV Currently Tuning MI-8 line and MI MI-10 kicker upgrades seem to have worked.

Slide14: 

Technical Status

Major Elements: 

Major Elements Linac (1.1) (1.1.1) Reliability Bad 7835 (of the 12) returned for checkout. (1.1.4) LEL LLRF (Improve phase and amplitude stability) Shutdown characterization studies complete (1.2) Booster (1.2.3) New Corrector System (See Drennan’s talk) (1.2.4) 30 Hz Harmonic Waiting to de-scope (1.3) Main Injector (1.3.2) MI Collimation Systems MI-8 collimator completed in the shutdown Will review ring collimation scheme in June (1.3.4) MI RF Upgrade Studies continue

Revised Projections: 

Revised Projections We are working to revise projection in preparation for the next Director’s Review The biggest correction is for the benefit from NuMI slip stacking: Originally assumed that we began to implement slip stacking gradually over a year following this shutdown Now assume we do studies over the next year, but don’t get any benefit from slip stacking until after collimation and/or RF improvements in the 2007 shutdown, but then it only takes three months to ramp up. These new projections were presented at the AAC review.

Long Term Projections: 

Long Term Projections These projections do not take in to account effects of collider turning off or possible improvements thereafter.