Presentation Transcript
Slide1: M6 Motorway PPP Project, Hungary: A Case Study
David Asteraki, ING Bank NV
IFSL PPP Seminar, Athens 26th May 2005
PPP Road ProjectsA great international success: PPP Road Projects A great international success Widely used across Europe, North America, Asia, Australia, South Africa, etc.
Numerous studies have demonstrated value for money
There is keen interest from:
Construction contractors
Operators
Financial investors
Debt financiers (banks, bond investors, bond insurers)
Procurement can be quick and efficient
M6 Motorway Procurement TimetableAn international record: M6 Motorway Procurement Timetable An international record M6 Motorway, Hungary
Based on availability payments
1st stage tender (pre-qualification) launched 31 January 2004
2nd stage tenders (3) submitted 19 July 2004
Project Contract signed 2 October 2004
Financial Close 15 December 2004
10½ months in total
ING advised Hungarian Government
M8 Fermoy Bypass, Ireland
Based on mix of real tolls and construction & operating grants
Pre-qualification launched June 2002
Initial tenders (4) submitted November 2002
BaFOs (2) submitted December 2003
Project Contract signed and Financial Close June 2004
2 years in total
ING arranged and provided debt finance
M6 Motorway Project, Hungary: M6 Motorway Project, Hungary Awarded by National Motorway Company on behalf of Ministry of Economy and Transport
Awarded to consortium of Bilfinger Berger, Porr & Swietelsky
Final design, construction, financing, operation and maintenance of motorway over 22 years
58 km of dual two-lane motorway, 10 junctions, 54 bridges between Érdi tető (SW of Budapest) and M8 at Dunaújváros
Includes some works to local roads
Total Project value approximately €480 million
€411 million of debt finance with tenor of 20.5 years
Hungary: Planned Motorway Network to 2015M6 forms key part: Hungary: Planned Motorway Network to 2015 M6 forms key part
M6 Motorway Project: A Great Success: M6 Motorway Project: A Great Success Procured in record time
Construction timetable meets Government objectives
Good risk transfer to private sector
4 strong international consortia submitted 1st stage bids
3 strong 2nd stage bids received
Government’s risk allocation broadly maintained
Good Value for Money
Construction, O&M and finance costs all competitive
Why was the M6 Project such a success?: Why was the M6 Project such a success? Strong political support and commitment
Supportive public sector decision making process
Sensible approach to market
Standard risk allocation
Standard Project Contract and Financiers’ Direct Agreement
Availability-based payment mechanism
No net traffic risk
High quality public sector advisors
Strong Political Support and Commitment: Strong Political Support and Commitment Government as a whole committed to PPP projects
Strong personal support from Minister of Economy and Transport Istvan Csillag and his deputy Imre Rethy
Absence of real tolls paid by motorists reduced political risk
Renegotiation of M5 Motorway Project gave good precedent
Political imperative to remove real tolls required PPP structure
Initial support and commitment made decision making and approval much easier
Effective public sector decision making process: Effective public sector decision making process Negotiating team had:
Clear, realistic mandate with delegated decision authority
Ready access to ultimate decision makers (Ministers Csillag & Rethy)
Strong leader (Fruzsina Biro) with commercial experience
Commitment and willingness to work hard!
There were no rival decision makers
All parties bought into negotiating team’s mandate
Sensible approach to market: Sensible approach to market Announcement in international press
Well developed initial information package
Project description
Initial design
Indicative risk matrix
Payment mechanism
Transparent criteria for selecting tenderers
Well developed Invitation to Tender/Negotiate
Full draft Project Contract including schedules
Transparent criteria for selecting winning tender
Standard risk allocationBased on market standards that have built up over time: Standard risk allocation Based on market standards that have built up over time No significant deviations that favoured the public sector:
Minimised delays and legal costs during negotiations
Maximised value for money due to familiarity with risk
No unmanageable risks
Public sector bears risk of approvals, land acquisition, etc.
Eurostat rules now favourable to standard PPP projects:
Private sector need bear only minimum of construction risk and either demand risk or availability risk for Project to be off balance sheet
Key issue is compensation on termination for default
Compensation 65% of value of Project to the Government
No automatic full repayment of debt
Project Contract and Financiers’ Direct Agreement: Project Contract and Financiers’ Direct Agreement Based on existing precedents (UK OGC Guidance)
Familiarity among tenderers and advisors shortened negotiations
Risk allocation is more obvious
Limited need for new drafting, minimising legal costs
UK OGC Guidance is widely accepted
English language used, even though under Hungarian law
Made project more attractive to international tenderers
Eliminated translation costs and time
Availability-based payment mechanismPrivate sector bearing traffic risk reduces value for money: Availability-based payment mechanism Private sector bearing traffic risk reduces value for money Private sector has very limited ability to manage or mitigate
However, investors and financiers have been willing to bear it
Private sector bearing ANY net traffic risk lengthens procurement period and adds to tender costs
Tenderers and their financiers both require detailed analysis
Financiers particularly are conservative and require higher margins and cover ratios
“Green field” project reduce predictability of traffic volumes
Overall, likely to lead to more expensive project
How do availability payments work?: How do availability payments work? Predefined level of gross payments (focus of tender)
Payment deductions for unavailability depending on:
Length of road affected
Number of lanes affected
The use of contraflow (on grounds of reduced safety)
Duration of unavailability
Time of day (higher in peak hours), day of week, season
Lanes “unavailable” if not usable or unsafe
Periods of maintenance included, to incentivise minimum disruption
Exclusions for external events (snow, accidents)
Additional deductions for poor performance of services
Strengths and weaknesses of availability payments: Strengths and weaknesses of availability payments No politically difficult real tolls
No private sector traffic risk premium
Minimises Project cost
Procurement period minimised
No need to undertake traffic studies
BUT
Not favoured by EU (prefer “user pays”)
High impact on public sector budget
Public sector advisorsFinancial, legal, technical: Public sector advisors Financial, legal, technical Extensive international experience
True for team members as well as company
Depth of resources
Fee rates may be high for quality advisors, BUT their experience leads to:
More efficient procurement with likely lower overall cost
Better value for money project
Using cheap but inexperienced advisors is false economy