Presentation Transcript
Metropolitan Porto Light Rail System: European Federation of Railways Trackworks Contractors
June 24th 2005 Metropolitan Porto Light Rail System Project Presentation
Slide2: PROJECT DEVELOPMENT
ENGINEERING
COMMERCIAL OPERATION
INTERMODALITY IN AMP
LINES IN OPERATION
NEW PROJECTS
Slide3: PROJECT DEVELOPMENT
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
I. Project Development: I. Project Development GAIA LINE TROFA LINE MATOSINHOS LINE Dragão PÓVOA LINE Campanhã Initial Contract 876 M €
Project Changes 2001 193 M €
Red Line duplication 100 M €
Green Line duplication 106 M €
Campanhã –Dragão line 50 M€
Airport Line 42 M€ Airport Ismai
I. Project Development: I. Project Development INVESTMENT & FINANCING INVESTMENT
Slide6: PROJECT EVOLUTION
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
II. Engineering: II. Engineering 3 Tunnels excavated with TBM-EPB (6,1 km)
Underground stations
Heroísmo
Campo 24 de Agosto
Bolhão
Salgueiros
Faria Guimarães
Marquês
Combatentes
S. Bento
Aliados
UNDERGROUND WORKS
II. Engineering: II. Engineering FUNCTIONAL MAP OF THE NETWORK
II. Engineering Tunnel works: II. Engineering Tunnel works Close Mode: to control over-excavation risks
Appropriate support pressure
Integrated design team on site
Independent design check procedure TBM-EPB WORKS METHODOLOGY
II. Engineering Tunnel works: II. Engineering Tunnel works Automatic slurry injection in the working chamber to maintain the support pressure
Double piston pump
TBM monitoring on a real time basis
TBM-EPB WORKS METHODOLOGY
II. Engineering: II. Engineering Tunnel
Extension 2,3 km
Diameter 7,8 m
Beginning of excavation 14/6/2000
End of excavation 21/10/2002
Volume of excavated material 138.000 m3
Cost (without underground stations) 38 M €
Ring
Universal type 6+1
Length 1400 mm
Thickness 300 mm
Concrete C40/50 TUNNEL OF LINE A
II. Engineering: II. Engineering Tunnel
Extension 3,8 km
Diameter 8 m
Beginning of excavation 11/6/2002
End of excavation 3/11/2003
Volume of excavated material 228.000 m3
Cost (without underground stations) 53 M €
Ring
Universal type 6+1
Length 1400 mm
Thickness 300 mm
Concrete C40/50 TUNNEL OF LINE D
II. Engineering Tunnel works: II. Engineering Tunnel works Simplified station layouts
Unified solutions and construction methods when possible
Design team on site to adapt methods to real conditions UNDERGROUND STATIONS METHODOLOGY
II. Engineering Underground Stations: II. Engineering Underground Stations Faria Guimarães
Station
Cost: 23,5 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering Marquês
Station
Cost: 22 M € Salgueiros
Station
Cost: 23 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering Heroísmo
Station
Cost: 25 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering S. Bento
Station
Cost: 22 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering Bolhão
Station
Cost: 25 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering Aliados
Station
Cost: 23 M € UNDERGROUND STATIONS
II. Engineering: II. Engineering SURFACE
II. Engineering: II. Engineering SURFACE
II. Engineering: II. Engineering SURFACE S. João Hospital
II. Engineering: II. Engineering DIRECT COST PER QUILOMETER
II. Engineering: II. Engineering LUIZ I BRIDGE Designed by Théophile Seyrig.
Constructed between 1881 and 1886.
Opened on the 31st of October 1886.
Upper deck of 400m long.
Seven columns.
Arch with 172 m span and 45 m rise.
II. Engineering: II. Engineering LUIZ I BRIDGE Main anomalies detected:
Paint detachment and corrosion points;
Loss of rivets;
Structure’s coating deterioration;
Moisture and water infiltration;
Corrosion at connection nodes;
“Trellis” plates buckling;
Lower flange plate buckling;
Very intense corrosion in some connection plates of the transversal bracing.
II. Engineering: II. Engineering LUIZ I BRIDGE Rebuilding work:
Total replacement of the upper deck.
Reinforcement of main beam diagonals.
Reinforcement of column diagonals.
Reinforcement of suspension elements.
Reinforcement of diagonals on the arch plane.
Reinforcement of the vertical transversal bracing diagonals.
Replacement of all corroded elements.
Repair and replacement of the bearings.
Total painting.
II. Engineering: II. Engineering LUIZ I BRIDGE - Road width……………………………….…..……..5,520 m *
Sidewalks.………………..…………………..……..1,355 m *
Total width……………………………………..…….8,230 m * - Railway width……………………………....……..6,400 m
Sidewalks..…………………………………..……..1,700 m
Total width..…………………………………..…….9,800 m General data before intervention General data after intervention Cost: 7,4 M €
II. Engineering: Bridge‘s scaffolding Sidewalk and rail sleepers II. Engineering LUIZ I BRIDGE
II. Engineering: Total length: 497,2 m
Spans: 24.80m + 5 x 30.60m + 40.50m + 5 x 30.60m + 40.50m + 48.80m + 36.60m = 497.20 m
Structure: Continuous beam, in a steel-concrete composite structure, supported by 14 reinforced concrete columns and 2 abutments, through neoprene pot-bearings. Located on the Green Line (Fonte do Cuco / Trofa) between the stations of Custió and Parque in the city of Maia. II. Engineering PARQUE DA MAIA VIADUCT Parque da Maia Viaduct longitudinal section Cost: 6,8 M €
II. Engineering: Parque station:
The deck’s cross-section width enlarges from10,10 meters to 13,75 meters. II. Engineering PARQUE DA MAIA VIADUCT Parque da Maia Station Construction method
The construction phasing together with the metallic beams slenderness and the fact that the beams are used for the slab’s concreting led to use an opposite deformation at manufacturing.
The slab’s concreting was done:
in a first phase on the spans
in a second phase over the columns, in order to reduce the concrete shrinking stresses.
II. Engineering: Viaduto Maia Norte Located on the Green Line (Fonte do Cuco / Trofa) between the stations of Forum and Zona Industrial in the city of Maia.
Connects Travessa dos Brandinhais and the Industrial District.
Total length: 524,40 meters. II. Engineering MAIA NORTE’S VIADUCT Maia Norte Viaduct – Side view Cost: 6,0 M €
II. Engineering: Technical Specification:
Continuous beam, in a steel-concrete composite structure, supported by 14 reinforced concrete columns and 2 abutments.
Total length: 524,40m
Spans: 22.80m + 7x34.20m + 2x39.90m + 45.60m + 2x39.90m + 34.20m + 22.80m.
Deck’s total width: 12.00m.
2 steel beams and a reinforced concrete slab.
Total height: 2,50m, as the steel beam is 2,00m high and the concrete slab’s maximum thickness is 0,50m.
Y-shaped concrete columns with a variable height ranging from 4.20m to 16.70m.
Pile foundations with groups of 5 or 6 1,00m diameter piles by column. II. Engineering MAIA NORTE’S VIADUCT
II. Engineering: Automatic Vehicle Regulation
ATP – Automatic Train Protection (Ebicab 900)
TMS (Traffic Management System) with powerful control and regulation tools II. Engineering SIGNALING SYSTEMS
II. Engineering: II. Engineering SIGNALING SYSTEMS Initial System Upgrading Supplier: Bombardier Transportation
Slide35: PROJECT EVOLUTION
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
III. Lines in Operation: III. Lines in Operation Dec 2002 Jun 2004 Mar 2005 Póvoa do Varzim Sra. da Hora Trindade Dragão Sto Ovídeo Hospital S João Trofa Matosinhos Ismai Pedras Rubras Gondomar Aeroporto Conclusion of entire approved network in the next 8 months (except Ismai-Trofa)
Demand forecast 1.8 Million P*Kms/year
Slide37: PROJECT EVOLUTION
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
IV. Intermodality in AMP: IV. Intermodality in AMP Created in December 2002:
Metro do Porto
STCP
USGP/CP
Main Goals:
Create a common zoning in AMP and Trofa
Create and manage an integrated ticketing system
Implement a revenue sharing model between operators TIP, ACE
IV. Intermodality in AMP: IV. Intermodality in AMP Contact-less technology
Andante cards
CTS
GTML2 – Andante Gold
COMMON TICKETING SYSTEM
IV. Intermodality in AMP: Andante Products
0ccasional Tickets
Voyage Ticket
Andante 24
Valid 24 hours after the first validation
Season Tickets
Monthly Ticket
Andante 10-16
Valid in the 10h-16h period in the working days and without any restrictions in the weekends and holidays IV. Intermodality in AMP COMMON PRICING
Slide41: PROJECT EVOLUTION
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
V. Commercial Operation: V. Commercial Operation NUMBER OF VALIDATIONS 82% increase on weekday average in (May 2004 vs May 2005)
Average covered distance of 4,7 kms (2004) Average commercial speed of 24,7 kms/h (2004)
Occupation rate of 11,1% (2004)
V. Commercial Operation: V. Commercial Operation More than 1 M monthly validations
83% increase from 2003 to 2004
Occupation rate of 11,1% (2004)
Income: 11.26 cents per Pkm (2004)
Operational cost: 2.85 cents per Seat km (2004)
Dec 04: 49% of 2008 Blue Line forecast demand reached, Forecast considering entire network in operation for 3 years and bus network restructured to feed metro
Since Sep 04: more than 100% of this demand achieved, in morning peak hour on urban stretches in Porto
Slide44: PROJECT EVOLUTION
ENGINEERING
LINES IN OPERATION
INTERMODALITY IN AMP
COMMERCIAL OPERATION
NEW PROJECTS
VI. New Projects: VI. New Projects NETWORK Duplication of Green Line
Yellow Line Extension
Gondomar Line
Boavista Line
and…
Gaia Line II
Maia Line II
VI. New Projects: VI. New Projects GAIA TROFA MATOSINHOS Airport PÓVOA 1. DUPLICATION OF GREEN LINE Ismai Pateiras PORTO Length 8,7 kms
Number of Stations 5
Additional Budget 46 M €
VI. New Projects: VI. New Projects 2. YELLOW LINE EXTENSION Length 1,4 kms
Number of Stations 3
Sto. Ovídeo
Cravel
Quinta do Cedro
Demand 78 Thousand P*Kms/Y
Budget 76,7 M €
Laborim Depot 36 M €
GAIA LINE TROFA LINE MATOSINHOS LINE Dragão PÓVOA LINE Sto. Ovídeo Laborim Airport
VI. New Projects: VI. New Projects GONDOMAR
LINE 11 kms
80 M Pass.kms 3. GONDOMAR LINE Length 11 kms
Number of Stations 17
Demand 295 Thousand P*Kms/Y
Budget 201 M €
VI. New Projects: VI. New Projects 4. BOAVISTA LINE BOAVISTA LINE Length 7 kms
Number of Stations 17
Demand 88 Thousand P*Kms/Y
Budget 139 M €
Metropolitan Porto Light Rail System: European Federation of Railways Trackworks Contractors
June 24th 2005 Metropolitan Porto Light Rail System Project Presentation