Cape Recovery Plan Update: 

Cape Recovery Plan Update Jacob Maroga 24 May 2006

Objectives: 

Objectives Recap Cape Recovery challenges and key mitigating activities Provide a progress update on Cape Recovery activities Outline the medium term Cape Recovery initiatives

Western Cape Network – Load and Capacity: 

Western Cape Network – Load and Capacity Eskom Peaking Generation 400 MW Palmiet Note: The above excludes The City of Cape Town’s generation Load Winter Max : 4250 MW Summer Max : 3900 MW Transmission Capacity 3500 Koeberg Generation 1800 MW

Predicted Weekly Shortfall: 

Predicted Weekly Shortfall Shortfall Risk: 300 to 400 MW during morning and evening peaks Unit 1 Unit 1 and 2 Unit 2

Key Recovery Activities: 

Key Recovery Activities Supply / Capacity Recovery Activities Koeberg Generation Transmission Grid Leased-in Generation Demand / Load Reduction Activities Energy Saving programmes Demand Side Management Demand Market Participation Network Optimisation Load Shedding When demand exceeds supply

Progress – Koeberg repairs on track: 

Progress – Koeberg repairs on track

Progress – View of Koeberg repairs: 

Progress – View of Koeberg repairs

Progress – Transmission on track: 

Progress – Transmission on track

Progress – Replacing insulators: 

Progress – Replacing insulators Live Line work to replace insulators

Progress – Leased-in Generation on track: 

Progress – Leased-in Generation on track Three 22 MW leased-in generators on site at PetroSA Commercial operation on track for 3rd week of May 2006 Progress to date Construction of the fuel line from the tank farm to the leased plant site complete Temporary 132 kV busbar constructed Cabling installations complete Commissioning in final stages

Progress – Energy Savings to date: 

Progress – Energy Savings to date

Update – Load Shedding to date: 

Update – Load Shedding to date Load Shedding is required during periods where energy demand exceeds supply capacity No load shedding has taken place since 11 April past Weekly schedules are published in the newspapers a week in advance

Medium Term Plans for Recovery: 

Medium Term Plans for Recovery Demand Side Management (DSM) Continue short term DSM programmes in medium to long term Explore additional measures for implementation in the medium term Solar Water Heating Cogeneration Time Of Use Tariffs Establish a task team to investigate the feasibility of alternative DSM options, with associated business plan and targets Build Generating Plants Two liquid fuel generating plants are being built in Atlantis and Mossel Bay at a cost of R3.5bn Designed for peaking capacity Total capacity of approximately 1050MW Target completion before the winter of 2007 Strengthen the Transmission Grid Plans to reinforce the Cape Network at advanced stage with investment decisions expected in 2006