Okereke King County

Uploaded from authorPOINT
Views:
 
     
 

Presentation Description

No description available.

Comments

Presentation Transcript

4th Annual Regional Contracting ForumMarch 07, 2006: 

4th Annual Regional Contracting Forum March 07, 2006 KING COUNTY SOLID WASTE DIVISION ENGINEERING SERVICES SECTION Presented By Victor O. Okereke, Ph.D.,P.E.,DEE (206) 296-4422

ARCHITECTURAL/ENGINEERING CONSULTANT PROJECTS & CONTRACTS: 

ARCHITECTURAL/ENGINEERING CONSULTANT PROJECTS andamp; CONTRACTS PROJECT #1A – CEDAR HILLS REGIONAL LANDFILL AREA 6 CLOSURE SCOPE OF WORK – DESIGN SERVICES The scope of the CH Refuse Area 6 Final Cover Project Includes multiple phases of Design, design services during construction and preparation of updates to existing plans of operations. PROJECTED COST FOR DESIGN SERVICES: $2.2 million PROJECT MANAGER: NOT-YET-ASSIGNED PROCUREMENT PROCESS: Advertised (2nd Quarter) PROJECT #1B – CONSTRUCTION MANAGEMENT SERVICES FOR AREA 6 CLOSURE andamp; AREA 7 DEVELOPMENT SCOPE OF WORK – DESIGN SERVICES To provide construction management services for Area 6 Closure and Area 7 development. PROJECTED COST:CONSTRUCTION MANAGEMENT SERVICES: $1.4 million PROJECT MANAGER: NOT-YET-ASSIGNED PROCUREMENT PROCESS: Advertised (2nd Quarter)

Slide3: 

PROJECT #2 – TRANSFER STATION SCADA SYSTEM MAINTENANCE SCOPE OF WORK Transfer Station SCADA operation and maintenance services PROJECTED CONSULTANT COST: $10,000.00 PROJECT MANAGER: Jamey Barker, P.E. PROCUREMENT PROCESS: Small Work Roster (3rd Quarter) PROJECT #3 – CEDAR HILLS SCADA SYSTEM MAINTENANCE SCOPE OF WORK CH SCADA operation and maintenance services. PROJECTED CONSULTANT COST: $10,000.00 PROJECT MANAGER: Jamey Barker, P.E. PROCUREMENT PROCESS: Small Work Roster (3rd Quarter)

Slide4: 

PROJECT #4 – ON-CALL ELECTRICAL ENGINEERING SERVICES SCOPE OF WORK The consultant selected for this contract will provide on-call electrical engineering services to primarily support the King County Solid Waste Division’s Capital Asset Maintenance Program. PROJECTED CONSULTANT COST: $200,000.00 PROJECT MANAGER: Francis Gaspay PROCUREMENT PROCESS: Small Work Roster (2nd Quarter) PROJECT #5 – ON-CALL ARCHITECTURAL SERVICES SCOPE OF WORK The consultant selected for this contract will provide on-call Architectural services to primarily support the King County Solid Waste Division’s Capital Asset Maintenance Program. PROJECTED CONSULTANT COST: $200,000.00 PROJECT MANAGER: Francis Gaspay PROCUREMENT PROCESS: Small Work Roster (2nd Quarter)

Slide5: 

PROJECT #6 – CEDAR HILLS REGIONAL LANDFILL PUMP STATION andamp; CONVEYANCE SYSTEM MODIFICATIONS SCOPE OF WORK Design of new Leachate /Wastewater pump stations andamp; modifications to existing pump stations at the Cedar Hills Regional Landfill. PROJECTED CONSULTANT COST: $250,000.00 PROJECT MANAGER: Fred Bennett, P.E. PROCUREMENT PROCESS: Advertised (1st Quarter)

CONSTRUCTION PROJECTS: 

CONSTRUCTION PROJECTS PROJECT #1 – ENUMCLAW TS SEISMIC RETROFIT SCOPE OF WORK Upgrade Enumclaw Transfer Station to current building code Standards for Seismic Design. PROJECTED CONSTRUCTION COST: $1.1 million PROJECT MANAGER: Tom Creegan, P.E. PROCUREMENT PROCESS: Advertised (2nd Quarter)

Slide7: 

PROJECT #2 – CEDAR HILLS FLARE STATION RELOCATION SCOPE OF WORK Relocate Flare Station PROJECTED CONSTRUCTION COST: $560,000.00 PROJECT MANAGER: Jamey Barker, P.E. PROCUREMENT PROCESS: Advertised (2nd Quarter)

Slide8: 

PROJECT # 3 – CEDAR HILLS FACILITY SHOP AND STORES PAINTNG SCOPE OF WORK Painting of Store and Shop Facilities. PROJECTED CONSTRUCTION COST: $71,000.00 PROJECT MANAGER: Tien Pham PROCUREMENT PROCESS: Advertised (2nd Quarter) PROJECT #4 – CEDAR HILLS RE-CONFIGURE DEADLINE TRAILER STORAGE AREA SCOPE OF WORK Projects will provide additional trailer parking at the existing upper parking lot. PROJECTED CONSTRUCTION COST: $25,000.00 PROJECT MANAGER: Tien Pham PROCUREMENT PROCESS: Small Work Roster (2nd Quarter)

Slide9: 

PROJECT #5 – CEDAR HILLS LEACHATE LINE INSPECTION SCOPE OF WORK Inspection of leachate line at Cedar Hills. PROJECTED CONSTRUCTION COST: $150,000.00 PROJECT MANAGER: Tien Pham PROCUREMENT PROCESS: Advertised (2nd Quarter) PROJECT #6 – HOBART CLOSED LANDFILL FACILITY IMPROVEMENT SCOPE OF WORK Work involves replacement and construction of a shelter for the Flare station blower, re-coating ,enclosing the ground flare, pipe replacement and other related works PROJECTED CONSTRUCTION COST: $120,000.00 PROJECT MANAGER: Jamey Barker, P.E. PROCUREMENT PROCESS: Advertised (4th Quarter)

Slide10: 

PROJECT #7 – PUYALLUP LF WELL HEAD PROTECTION SCOPE OF WORK Route existing gas extraction system well heads to a centralized location, to be fenced and secured from vandalism. PROJECTED CONSTRUCTION COST: $160,000.00 PROJECT MANAGER: Jamey Barker, P.E. PROCUREMENT PROCESS: Small Work Roster (2nd Quarter) PROJECT #8 – CEDAR FALLS SCALE-DECK REPLACEMENT SCOPE OF WORK Contractor to remove existing scale-deck and install new scale- deck. PROJECTED CONSTRUCTION COST: $35,000.00 PROJECT MANAGER: Francis Gaspay PROCUREMENT PROCESS: Small Work Roster (2nd Quarter)

Slide11: 

PROJECT #9 – CEDAR HILLS REGIONAL LANDFILL PUMP STATION PHASE I CONSTRUCTION SCOPE OF WORK Phase 1 Construction – Includes the construction of a replacement pump station and associated facilities at the Cedar Hills Regional Landfill, PROJECTED CONSTRUCTION COST: $470,000.00 PROJECT MANAGER: Fred Bennett, P.E. PROCUREMENT PROCESS: Advertised (3rd Quarter)