GDB Achievements Agreed on recommendations of 5 working groups
Established LCG-1 technology baseline
Integrated Middleware from European Data Grid (V 2.0) and US Virtual Data Toolkit (V 1.1.8+)
Agreed on preliminary model of operation 24hx24hx7
Grid Operation Centers
Identified major issues in security and operation
Being addressed by the LCG deployment area
Solutions with implications on RC or experiments to be agreed by GDB
Agreed on LCG support model
Hierarchical layered model
Experiments, Regional Support Centres, Grid Operation Centers
Resource Coordination:
Resource Coordination The GDB
Keeps track of the available resources based on input from the Country Representatives
Receives resource requests from the Experiments after validation by the PEB
Endorses resource allocation on the basis of the proposal made by the LCG Resource Coordinator that interacts with the Experiments and Regional Centre Representatives
Bernd Panzer was recently appointed as RC
Resources Declared Available:
Resources Declared Available Updated information for 2004 & 2005 was not yet available for all funding agencies due to different funding procedures in each particular country.
The capacity listed for 2003 does not correspond to the total capacity available to LHC, as only parts of the capacity of many centres will be included in LCG-1.
This LCG fraction will evolve according to the LCG deployment schedule and is expected to reach 1 everywhere at the beginning of 2004.
Resources Declared Available 2003:
Resources Declared Available 2003
Resources Declared Available 2004:
Resources Declared Available 2004
Resources Declared Available 2005:
Resources Declared Available 2005
Updates:
Updates Hungary has just declared the availability of regional centre resources for LCG.
These numbers and any other changes will be available on the regularly updated web site:
web.cern.ch/LCG/PEB/rc_resources/